4520 N GENTRY AVE 91607
Certificate Information: 4520 N GENTRY AVE 91607
- Application / Permit
- 21010-20000-06234
- Plan Check / Job No.
- B21VN16607
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 60' X 60'-4" TWO STORY SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED GARAGE AND ATTACHED OPEN TRELLIS; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/16/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | SELLA BENYAMIN |
| Corrections Issued | 1/11/2022 | SELLA BENYAMIN |
| Quality Review Completed | 1/13/2022 | STEVEN KIM |
| Building Plans Picked Up | 1/13/2022 | APPLICANT |
| Plan Check Approved | 6/2/2022 | SELLA BENYAMIN |
| Issued | 8/16/2022 | APPLICANT |
| CofO in Progress | 7/11/2023 | JACK KARGODORIAN |
| Permit Finaled | 12/19/2023 | RUBEN SALAS |
| CofO Issued | 12/19/2023 | RUBEN SALAS |
| Permit Finaled | 12/19/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/20/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/14/2022 | DWIGHT SANKEY |
| Low Impact Development | Cleared | 4/19/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 4/25/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 8/24/2022 | No Access for Inspection | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 8/24/2022 | Approved | CHRISTOPHE COCHRAN |
| Piling/Pier/Caisson | 8/24/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Underground Mechanical | 9/16/2022 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/27/2022 | Partial Approval | DAVID MATSON |
| Deputy Reinf. Concrete | 10/3/2022 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 10/13/2022 | Partial Approval | JACK KARGODORIAN |
| Deputy Shotcrete | 10/14/2022 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2022 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 11/18/2022 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 11/23/2022 | Approved | ROBERT GOLD |
| Piling/Pier/Caisson | 11/23/2022 | Not Ready for Inspection | ROBERT GOLD |
| Deputy Reinf. Concrete | 11/29/2022 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 12/8/2022 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2023 | Partial Approval | JACK KARGODORIAN |
| Deputy Wood Construction | 1/17/2023 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Partial Approval | JACK KARGODORIAN |
| HVAC-Rough | 2/15/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 2/15/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/21/2023 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 2/21/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 2/24/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 2/24/2023 | Approved | JACK KARGODORIAN |
| Green Building Rough | 2/24/2023 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 2/24/2023 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 2/24/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 3/10/2023 | Approved | JACK KARGODORIAN |
| HVAC-Final | 6/21/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 6/21/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 6/29/2023 | Corrections Issued | DAVID MATSON |
| Service/Power Release | 6/29/2023 | Not Ready for Inspection | DAVID MATSON |
| Final | 7/3/2023 | Not Ready for Inspection | DAVID MATSON |
| Green Building Final | 7/3/2023 | Approved | DAVID MATSON |
| MERV13>=Final | 7/3/2023 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Approved | DAVID MATSON |
| Smoke Detectors | 7/3/2023 | Approved | DAVID MATSON |
| ELECTRICAL-Final | 7/10/2023 | Approved | JACK KARGODORIAN |
| Final | 7/10/2023 | OK to Issue CofO | JACK KARGODORIAN |
| Service/Power Release | 7/10/2023 | Approved | JACK KARGODORIAN |