7866 N MATILIJA AVE 91402
Certificate Information: 7866 N MATILIJA AVE 91402
- Application / Permit
- 21010-20000-06214
- Plan Check / Job No.
- B21VN16530
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW DETACHED 45'5"X19' ACCESSORY DWELLING UNIT. ALL WORK PER WFPP. "The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit."
- Permit Issued
- Issued on 5/19/2022
- Issuing Office
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 12/12/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 4/26/2022 | HAYATO TSUCHIYA |
| Plan Check Approved | 5/9/2022 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 5/9/2022 | APPLICANT |
| Issued | 5/19/2022 | APPLICANT |
| CofO in Progress | 4/2/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 4/16/2024 | RUBEN SALAS |
| CofO Issued | 4/16/2024 | RUBEN SALAS |
| Permit Finaled | 4/16/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/13/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/20/2021 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 1/19/2022 | WALTER RAMIREZ |
| Construction within easement | Cleared | 1/19/2022 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 2/25/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/8/2023 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 9/18/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/18/2023 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2023 | Partial Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/23/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/23/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 10/23/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 10/23/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 10/23/2023 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 10/23/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 10/31/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/31/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Sewer | 10/31/2023 | Approved | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 11/2/2023 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 11/7/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 11/7/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 11/7/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Shower Pan | 11/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 11/7/2023 | Approved | GREGG CUMMINGS |
| Insulation | 11/15/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/15/2023 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 11/15/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 11/29/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/29/2023 | Partial Approval | GREGG CUMMINGS |
| Final | 3/6/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 3/6/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/6/2024 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 3/6/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 3/6/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 3/12/2024 | Corrections Issued | GREGG CUMMINGS |
| Service/Power Release | 3/12/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 3/12/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 3/18/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Service/Power Release | 3/18/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 3/18/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 3/21/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 3/21/2024 | Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 3/21/2024 | Approved | CHRISTOPHER ROJAS |