10336 N FERNGLEN AVE 91042

Certificate Information: 10336 N FERNGLEN AVE 91042

Application / Permit
21010-20000-06207
Plan Check / Job No.
B21VN16498
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE (1-STORY)
Permit Issued
Issued on 3/29/2023
Issuing Office
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 CARLOS MONTES
Corrections Issued 12/18/2021 CARLOS MONTES
Quality Review Completed 12/21/2021 LIPING TENG
Applicant returned to address corrections 3/16/2022 CARLOS MONTES
Applicant returned to address corrections 8/9/2022 CARLOS MONTES
Plan Check Approved 1/10/2023 CARLOS MONTES
Issued 3/29/2023 APPLICANT
CofO in Progress 3/26/2024 WILLIAM WREN
Permit Finaled 4/3/2024 RUBEN SALAS
CofO Issued 4/3/2024 RUBEN SALAS
Permit Finaled 4/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/4/2022 CARLOS AGUILERA
ZI Cleared 2/4/2022 LOUIS ORTEGA
Eng Process Fee Ord 176,300 Cleared 2/10/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 2/10/2022 BRIAN MILLER
Sewer availability Cleared 2/10/2022 CARLOS AGUILERA
Tenant Habitability Plan Cleared 3/23/2022 MICHAEL SOTO
Low Impact Development Cleared 5/10/2022 KHAING AYE
Roof/Waste drainage to street Cleared 5/13/2022 CARLOS AGUILERA
GPI Written Notices Cleared 8/9/2022 CARLOS MONTES

Contact Information

Contractor K N D Construction Inc; Lic. No.: 969756-B       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/21/2023 Partial Approval WILLIAM WREN
Sewer 6/21/2023 Approved WILLIAM WREN
Footing/Foundation/Slab 6/29/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/2/2023 Partial Approval MATTHEW NELSON
Deputy Wood Construction 8/11/2023 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 10/3/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 10/3/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Approved WILLIAM WREN
Green Building Rough 10/3/2023 Not Ready for Inspection WILLIAM WREN
HVAC-Rough 10/3/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 10/3/2023 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 10/3/2023 Approved WILLIAM WREN
Verify Sprinkler Sign Off 10/3/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 10/24/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 10/24/2023 Partial Approval WILLIAM WREN
Insulation 10/30/2023 Corrections Issued WILLIAM WREN
Insulation 11/3/2023 Corrections Issued WILLIAM WREN
Drywall Nailing 11/15/2023 Approved CHRISTOPHER ROJAS
Green Building Rough 11/15/2023 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/22/2023 Approved WILLIAM WREN
Shower Pan 11/22/2023 Approved WILLIAM WREN
Final 3/20/2024 OK to Issue CofO WILLIAM WREN
Green Building Final 3/20/2024 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 3/20/2024 SGSOV Approved WILLIAM WREN
Service/Power Release 3/20/2024 Approved WILLIAM WREN
Smoke Detectors 3/20/2024 Approved WILLIAM WREN