10203 N MONOGRAM AVE 91343

Certificate Information: 10203 N MONOGRAM AVE 91343

Application / Permit
21010-20000-06182
Plan Check / Job No.
B21VN16424
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 25' X 48' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.”
Permit Issued
Issued on 3/23/2022
Issuing Office
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2021 APPLICANT
Assigned to Plan Check Engineer 12/3/2021 RAPHAEL ROSAS
Corrections Issued 12/4/2021 RAPHAEL ROSAS
Applicant returned to address corrections 2/7/2022 RAPHAEL ROSAS
Plan Check Approved 3/21/2022 RAPHAEL ROSAS
Issued 3/23/2022 APPLICANT
Building Plans Picked Up 3/24/2022 APPLICANT
CofO in Progress 11/22/2022 JAVIER RAMOS JR
Permit Finaled 12/17/2022 MICHAEL SMITH
CofO Issued 12/17/2022 MICHAEL SMITH
Permit Finaled 12/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/10/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/15/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/15/2021 CARLOS AGUILERA
Sewer availability Cleared 12/15/2021 CARLOS AGUILERA
Construction near power lines Cleared 12/20/2021 WALTER RAMIREZ
Grading Pre-Inspection Cleared 1/13/2022 ALEXANDER ANDREWS
GPI Written Notices Cleared 3/21/2022 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/13/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 4/27/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 4/27/2022 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 5/18/2022 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/18/2022 Approved JAVIER RAMOS JR
Green Building Rough 5/18/2022 Not Ready for Inspection JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 5/18/2022 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 5/18/2022 Corrections Issued JAVIER RAMOS JR
Insulation 5/20/2022 Corrections Issued DEANDRE HOFFMAN
Shower Pan 5/20/2022 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 5/24/2022 Approved JAVIER RAMOS JR
Drywall Nailing 5/24/2022 Approved JAVIER RAMOS JR
Green Building Rough 5/24/2022 Approved JAVIER RAMOS JR
Insulation 5/24/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/24/2022 Partial Approval JAVIER RAMOS JR
Verify Sprinkler Sign Off 5/24/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 6/9/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 6/9/2022 Corrections Issued JAVIER RAMOS JR
Sewer 6/9/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Final 7/28/2022 Approved JAVIER RAMOS JR
Final 7/28/2022 Corrections Issued JAVIER RAMOS JR
Green Building Final 7/28/2022 Approved JAVIER RAMOS JR
HVAC-Final 7/28/2022 Approved JAVIER RAMOS JR
PLUMBING-Final 7/28/2022 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 7/28/2022 SGSOV Not Ready JAVIER RAMOS JR
Service/Power Release 7/28/2022 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 7/28/2022 Approved JAVIER RAMOS JR
Final 8/9/2022 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/9/2022 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 8/9/2022 Not Ready for Inspection JAVIER RAMOS JR
Final 11/22/2022 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 11/22/2022 Approved JAVIER RAMOS JR