10203 N MONOGRAM AVE 91343
Certificate Information: 10203 N MONOGRAM AVE 91343
- Application / Permit
- 21010-20000-06182
- Plan Check / Job No.
- B21VN16424
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25' X 48' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.”
- Permit Issued
- Issued on 3/23/2022
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2021 | RAPHAEL ROSAS |
| Corrections Issued | 12/4/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/7/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 3/21/2022 | RAPHAEL ROSAS |
| Issued | 3/23/2022 | APPLICANT |
| Building Plans Picked Up | 3/24/2022 | APPLICANT |
| CofO in Progress | 11/22/2022 | JAVIER RAMOS JR |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
| CofO Issued | 12/17/2022 | MICHAEL SMITH |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/10/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/15/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/15/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 12/20/2021 | WALTER RAMIREZ |
| Grading Pre-Inspection | Cleared | 1/13/2022 | ALEXANDER ANDREWS |
| GPI Written Notices | Cleared | 3/21/2022 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/13/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/27/2022 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/27/2022 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/18/2022 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/18/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 5/18/2022 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 5/18/2022 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 5/20/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Shower Pan | 5/20/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 5/24/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 5/24/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/24/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 5/24/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/24/2022 | Partial Approval | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 5/24/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 6/9/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/9/2022 | Corrections Issued | JAVIER RAMOS JR |
| Sewer | 6/9/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 7/28/2022 | Approved | JAVIER RAMOS JR |
| Final | 7/28/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 7/28/2022 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 7/28/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 7/28/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/28/2022 | SGSOV Not Ready | JAVIER RAMOS JR |
| Service/Power Release | 7/28/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 7/28/2022 | Approved | JAVIER RAMOS JR |
| Final | 8/9/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 8/9/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 8/9/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 11/22/2022 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 11/22/2022 | Approved | JAVIER RAMOS JR |