20441 W WILLOUGHBY LANE 91326

Certificate Information: 20441 W WILLOUGHBY LANE 91326

Application / Permit
21010-20000-06156
Plan Check / Job No.
B21VN16386
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE TWO STORY SFD WITH ATTACHED THREE CAR GARAGE_STANDARD PLAN#653_ PLAN 1AR _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 4/13/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 DAWN MC NULTY
Plans on Hold 12/29/2021 RARES BODEA
Hold Released 1/5/2022 DAWN MC NULTY
Corrections Issued 1/13/2022 DAWN MC NULTY
Quality Review Completed 1/19/2022 STEVEN KIM
Building Plans Picked Up 1/20/2022 APPLICANT
Plan Check Approved 4/4/2023 DAWN MC NULTY
Issued 4/13/2023 APPLICANT
CofO in Progress 2/10/2024 HENRY KIM
Permit Finaled 2/14/2024 JOHN JANSON
CofO Issued 2/14/2024 JOHN JANSON
Permit Finaled 2/14/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/19/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/19/2022 LEE GUILBEAUX
Permit Cleared 7/19/2022 LEE GUILBEAUX
Private street Cleared 7/19/2022 ASHLEY RODARTE
Public Works-Highway Ded. Cleared 7/19/2022 DAWN MC NULTY
Roof/Waste drainage to street Cleared 7/19/2022 LEE GUILBEAUX
Sewer availability Cleared 7/19/2022 LEE GUILBEAUX
Specific Plan Cleared 7/19/2022 ASHLEY RODARTE
"T" removal Cleared 7/20/2022 ASHLEY RODARTE
CPC Cleared 7/20/2022 ASHLEY RODARTE
Frnt yard landscape/Water mgmt Cleared 7/20/2022 ASHLEY RODARTE
Miscellaneous Cleared 7/20/2022 ASHLEY RODARTE
Miscellaneous Cleared 7/20/2022 ASHLEY RODARTE
Miscellaneous Cleared 7/20/2022 ASHLEY RODARTE
Tract Map conditions Cleared 7/20/2022 ASHLEY RODARTE
ZA Case Cleared 7/20/2022 ASHLEY RODARTE
ZA Case Cleared 7/20/2022 ASHLEY RODARTE
Low Impact Development Cleared 8/4/2022 AMMAR ELTAWIL
Hydrant and Access approval Cleared 10/5/2022 LAVEON RIDER
GPI Written Notices Cleared 4/4/2023 DAWN MC NULTY
Grading Pre-Inspection Cleared 4/4/2023 DAWN MC NULTY

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor Shapell Homes Inc; Lic. No.: 1001034-B 250 GIBRALTAR RD   ATTN-TAGERT/LEGAL    HOSHAM, PA 19044
Engineer Miller,, Karen Lynn; Lic. No.: GE2257 6634 VALJEAN AVENUE      VAN NUYS, CA 91406
Engineer Van, Gaale, Mark Allan; Lic. No.: C58680 185 W ORANGEWOOD AVE SUITE 200      ORANGE, CA 92868

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/11/2023 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 7/12/2023 Partial Approval HENRY KIM
Footing/Foundation/Slab 8/2/2023 Approved HENRY KIM
Deputy Reinf. Concrete 8/4/2023 Conditional Approval HENRY KIM
Sewer 8/11/2023 Not Ready for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Partial Approval HENRY KIM
Sewer 9/6/2023 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 9/11/2023 Partial Approval HENRY KIM
Underground Mechanical 9/20/2023 Approved HENRY KIM
Deputy Wood Construction 9/25/2023 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/26/2023 Corrections Issued HENRY KIM
Deputy Drilled-In Anchors 9/27/2023 Conditional Approval HENRY KIM
ELECTRICAL-Rough 9/27/2023 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Partial Approval HENRY KIM
HVAC-Rough 9/27/2023 Approved HENRY KIM
PLUMBING-Rough 9/27/2023 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 9/29/2023 Corrections Issued HENRY KIM
Green Building Rough 9/29/2023 Approved HENRY KIM
PLUMBING-Rough 9/29/2023 Approved HENRY KIM
Verify Sprinkler Sign Off 9/29/2023 Approved HENRY KIM
BUILDING-Rough-Frame 10/2/2023 Approved HENRY KIM
Interior/Exterior Lathing 10/3/2023 Partial Approval HENRY KIM
Interior/Exterior Lathing 10/10/2023 Partial Approval HENRY KIM
Drywall Nailing 10/13/2023 Approved HENRY KIM
Interior/Exterior Lathing 10/13/2023 Approved HENRY KIM
Gas Test 11/9/2023 Approved HENRY KIM
Service/Power Release 12/4/2023 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 12/13/2023 SGSOV Approved HENRY KIM
ELECTRICAL-Final 2/9/2024 Approved HENRY KIM
Final 2/9/2024 OK to Issue CofO HENRY KIM
Green Building Final 2/9/2024 Approved HENRY KIM
HVAC-Final 2/9/2024 Approved HENRY KIM
PLUMBING-Final 2/9/2024 Approved HENRY KIM
Smoke Detectors 2/9/2024 Approved HENRY KIM