11800 W TUDOR CT 91326
Certificate Information: 11800 W TUDOR CT 91326
- Application / Permit
- 21010-20000-06154
- Plan Check / Job No.
- B21VN16386
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE TWO STORY SFD WITH ATTACHED THREE CAR GARAGE_STANDARD PLAN#653_ PLAN 2C _ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 9/29/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2021 | DAWN MC NULTY |
| Plans on Hold | 12/29/2021 | RARES BODEA |
| Hold Released | 1/5/2022 | DAWN MC NULTY |
| Corrections Issued | 1/13/2022 | DAWN MC NULTY |
| Quality Review Completed | 1/19/2022 | STEVEN KIM |
| Building Plans Picked Up | 1/20/2022 | APPLICANT |
| Plan Check Approved | 9/26/2023 | DAWN MC NULTY |
| Issued | 9/29/2023 | APPLICANT |
| CofO in Progress | 6/28/2024 | HENRY KIM |
| Permit Finaled | 7/1/2024 | JOHN JANSON |
| CofO Issued | 7/1/2024 | JOHN JANSON |
| Permit Finaled | 7/1/2024 | JOHN JANSON |
Permit Application Clearance Information
| "T" removal | Cleared | 7/19/2022 | ASHLEY RODARTE |
| Address approval | Cleared | 7/19/2022 | LEE GUILBEAUX |
| CPC | Cleared | 7/19/2022 | ASHLEY RODARTE |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2022 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 7/19/2022 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 7/19/2022 | ASHLEY RODARTE |
| Miscellaneous | Cleared | 7/19/2022 | ASHLEY RODARTE |
| Permit | Cleared | 7/19/2022 | LEE GUILBEAUX |
| Private street | Cleared | 7/19/2022 | ASHLEY RODARTE |
| Public Works-Highway Ded. | Cleared | 7/19/2022 | DAWN MC NULTY |
| Roof/Waste drainage to street | Cleared | 7/19/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/19/2022 | LEE GUILBEAUX |
| Specific Plan | Cleared | 7/19/2022 | ASHLEY RODARTE |
| Tract Map conditions | Cleared | 7/19/2022 | ASHLEY RODARTE |
| ZA Case | Cleared | 7/19/2022 | ASHLEY RODARTE |
| ZA Case | Cleared | 7/19/2022 | ASHLEY RODARTE |
| Frnt yard landscape/Water mgmt | Cleared | 7/20/2022 | ASHLEY RODARTE |
| Low Impact Development | Cleared | 8/4/2022 | AMMAR ELTAWIL |
| Hydrant and Access approval | Cleared | 10/5/2022 | LAVEON RIDER |
| GPI Written Notices | Cleared | 9/26/2023 | DAWN MC NULTY |
| Grading Pre-Inspection | Cleared | 9/26/2023 | DAWN MC NULTY |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 1140 VIRGINIA DR ATTN: TOLL BROTHERS - TAGGERT/LEGAL FORT WASHINGTON, PA 19034 |
| Engineer | Miller,, Karen Lynn; Lic. No.: GE2257 | 6634 VALJEAN AVENUE VAN NUYS, CA 91406 |
| Engineer | Van, Gaale, Mark Allan; Lic. No.: C58680 | 185 W ORANGEWOOD AVE SUITE 200 ORANGE, CA 92868 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/10/2024 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 1/18/2024 | Approved | HENRY KIM |
| Deputy Reinf. Concrete | 1/19/2024 | Conditional Approval | HENRY KIM |
| Sewer | 1/25/2024 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2024 | No Access for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2024 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 2/16/2024 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 2/27/2024 | Partial Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2024 | Partial Approval | HENRY KIM |
| Deputy Drilled-In Anchors | 2/28/2024 | Conditional Approval | HENRY KIM |
| Deputy Wood Construction | 3/11/2024 | Conditional Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2024 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2024 | Partial Approval | HENRY KIM |
| Deputy Wood Construction | 3/14/2024 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 3/14/2024 | Partial Approval | HENRY KIM |
| HVAC-Rough | 3/14/2024 | Partial Approval | HENRY KIM |
| PLUMBING-Rough | 3/14/2024 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 3/18/2024 | Partial Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Approved | HENRY KIM |
| Green Building Rough | 3/18/2024 | Partial Approval | HENRY KIM |
| Interior/Exterior Lathing | 3/18/2024 | Partial Approval | HENRY KIM |
| Verify Sprinkler Sign Off | 3/18/2024 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 3/19/2024 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 3/19/2024 | Approved | HENRY KIM |
| Green Building Rough | 3/19/2024 | Approved | HENRY KIM |
| HVAC-Rough | 3/19/2024 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 3/19/2024 | Partial Approval | HENRY KIM |
| PLUMBING-Rough | 3/19/2024 | Approved | HENRY KIM |
| Drywall Nailing | 4/1/2024 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 4/1/2024 | Approved | HENRY KIM |
| Gas Test | 4/25/2024 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 5/3/2024 | SGSOV Approved | HENRY KIM |
| Service/Power Release | 5/20/2024 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 6/25/2024 | Approved | HENRY KIM |
| Final | 6/25/2024 | Corrections Issued | HENRY KIM |
| Green Building Final | 6/25/2024 | Approved | HENRY KIM |
| HVAC-Final | 6/25/2024 | Approved | HENRY KIM |
| PLUMBING-Final | 6/25/2024 | Approved | HENRY KIM |
| Smoke Detectors | 6/25/2024 | Approved | HENRY KIM |
| Final | 6/28/2024 | OK to Issue CofO | HENRY KIM |