5312 N WILKINSON AVE 91607
Certificate Information: 5312 N WILKINSON AVE 91607
- Application / Permit
- 21010-20000-06151
- Plan Check / Job No.
- B21VN16359
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT AND ADITION TO (E) GARAGE TO A NEW DETACHED ADU PER ORDINANCE (2-STORY)
- Permit Issued
- Issued on 3/15/2022
- Issuing Office
- Current Status
- CofO Issued on 2/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | CARLOS MONTES |
| Corrections Issued | 12/11/2021 | CARLOS MONTES |
| Quality Review Completed | 12/14/2021 | HERNAN ARREOLA |
| Plan Check Approved | 3/15/2022 | CARLOS MONTES |
| Issued | 3/15/2022 | APPLICANT |
| CofO in Progress | 12/26/2023 | JOSE AVILA |
| Permit Finaled | 2/13/2024 | RUBEN SALAS |
| CofO Issued | 2/13/2024 | RUBEN SALAS |
| Permit Finaled | 2/13/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/14/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/15/2021 | JOSE DUARTE-DIAZ |
| Specific Plan | Cleared | 12/22/2021 | ERIN NASH |
| Low Impact Development | Cleared | 1/28/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 1/31/2022 | JOSE DUARTE-DIAZ |
| Frnt yard landscape/Water mgmt | Cleared | 2/4/2022 | MIGUEL GAMBOA |
| Hold | Cleared | 11/7/2022 | JEREMY CORONEL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/24/2023 | Partial Approval | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 1/27/2023 | Not Ready for Inspection | KIRK SANDERS |
| Footing/Foundation/Slab | 2/7/2023 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2023 | Corrections Issued | KIRK SANDERS |
| Deputy Wood Construction | 2/22/2023 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2023 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 4/14/2023 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 4/14/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 4/14/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 4/26/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 4/26/2023 | Not Ready for Inspection | KIRK SANDERS |
| Interior/Exterior Lathing | 4/26/2023 | Partial Approval | KIRK SANDERS |
| Shower Pan | 4/26/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 5/2/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/22/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 5/22/2023 | Approved | KIRK SANDERS |
| Insulation | 5/22/2023 | Corrections Issued | KIRK SANDERS |
| Insulation | 5/26/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/12/2023 | Corrections Issued | RAUL OLAGI |
| Drywall Nailing | 6/14/2023 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 6/14/2023 | Approved | JOHN COLEMAN |
| Underground Mechanical | 6/30/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 11/2/2023 | No Access for Inspection | KIRK SANDERS |
| Final | 11/2/2023 | No Access for Inspection | KIRK SANDERS |
| Footing/Foundation/Slab | 11/2/2023 | No Access for Inspection | KIRK SANDERS |
| Green Building Final | 11/2/2023 | No Access for Inspection | KIRK SANDERS |
| HVAC-Final | 11/2/2023 | No Access for Inspection | KIRK SANDERS |
| PLUMBING-Final | 11/2/2023 | No Access for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/2/2023 | SGSOV Not Ready | KIRK SANDERS |
| Service/Power Release | 11/2/2023 | No Access for Inspection | KIRK SANDERS |
| Smoke Detectors | 11/2/2023 | No Access for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 11/21/2023 | Corrections Issued | JUAN VALENZUELA |
| Final | 11/21/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 11/21/2023 | Approved | JUAN VALENZUELA |
| Green Building Final | 11/21/2023 | Approved | JUAN VALENZUELA |
| HVAC-Final | 11/21/2023 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Final | 11/21/2023 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | JUAN VALENZUELA |
| Service/Power Release | 11/21/2023 | Corrections Issued | JUAN VALENZUELA |
| Smoke Detectors | 11/21/2023 | Approved | JUAN VALENZUELA |
| Final | 12/4/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 12/8/2023 | Approved | JOSE AVILA |
| Final | 12/8/2023 | Partial Inspection | JOSE AVILA |
| HVAC-Final | 12/8/2023 | Approved | JOSE AVILA |
| PLUMBING-Final | 12/8/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 12/13/2023 | Approved | JOSE AVILA |
| Final | 12/26/2023 | OK to Issue CofO | JOSE AVILA |