14531 W ASTORIA ST 91342
Certificate Information: 14531 W ASTORIA ST 91342
- Application / Permit
- 21010-20000-06145
- Plan Check / Job No.
- B21VN16351
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE WITH NEW ADDITION INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 1/25/2022
- Issuing Office
- Current Status
- CofO Issued on 7/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2021 | KEVIN MORALES |
| Corrections Issued | 12/1/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 12/28/2021 | KEVIN MORALES |
| Plan Check Approved | 1/1/2022 | KEVIN MORALES |
| Issued | 1/25/2022 | APPLICANT |
| CofO in Progress | 6/16/2022 | ARAM AVEDISIAN |
| CofO Issued | 7/16/2022 | MICHAEL SMITH |
| Permit Finaled | 7/16/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 12/7/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 12/14/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Polymath Development Group Inc; Lic. No.: 1069728-B | 1858 ECHO PARK AVE LOS ANGELES, CA 90026 |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/3/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 2/14/2022 | Corrections Issued | JOHN HAYES |
| Pre-Inspection | 2/14/2022 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 2/14/2022 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 2/18/2022 | Approved | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 2/18/2022 | Approved | MICHAEL TEMPLE |
| PLUMBING-Rough | 2/18/2022 | Partial Approval | MICHAEL TEMPLE |
| Underground Mechanical | 2/18/2022 | Approved | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 3/1/2022 | Not Ready for Inspection | JOHN HAYES |
| Deputy Wood Construction | 3/1/2022 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 3/1/2022 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 3/1/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 3/1/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 3/1/2022 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2022 | Partial Approval | JOHN HAYES |
| Insulation | 3/2/2022 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 3/2/2022 | Partial Approval | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 3/2/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 3/4/2022 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 3/4/2022 | Approved | JOHN HAYES |
| Green Building Rough | 3/4/2022 | Approved | JOHN HAYES |
| HVAC-Rough | 3/4/2022 | Approved | JOHN HAYES |
| PLUMBING-Rough | 3/4/2022 | Approved | JOHN HAYES |
| Insulation | 3/7/2022 | Not Ready for Inspection | JOHN HAYES |
| Shower Pan | 3/7/2022 | Approved | JOHN HAYES |
| Insulation | 3/10/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 3/10/2022 | Partial Approval | JOHN HAYES |
| Special/Order Compliance | 3/10/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 3/11/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 4/4/2022 | Approved | JOHN HAYES |
| Final | 6/3/2022 | No Access for Inspection | MATT KELLERMAN |
| Green Building Final | 6/3/2022 | No Access for Inspection | MATT KELLERMAN |
| Smoke Detectors | 6/3/2022 | No Access for Inspection | MATT KELLERMAN |
| Final | 6/7/2022 | Corrections Issued | JOHN HAYES |
| Final | 6/16/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| Green Building Final | 6/16/2022 | Approved | ARAM AVEDISIAN |
| Smoke Detectors | 6/16/2022 | Approved | ARAM AVEDISIAN |