7530 N SHOUP AVE 91307
Certificate Information: 7530 N SHOUP AVE 91307
- Application / Permit
- 21010-20000-06120
- Plan Check / Job No.
- B21VN16245
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ( 26'-0"x 25'-0") IRR SHAPED TWO-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 12/15/2022
- Issuing Office
- Current Status
- CofO Issued on 5/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2022 | TROY DEGUZMAN |
| Plans on Hold | 1/10/2022 | RARES BODEA |
| Hold Released | 1/18/2022 | TROY DEGUZMAN |
| Corrections Issued | 1/20/2022 | TROY DEGUZMAN |
| Quality Review Completed | 1/21/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 1/25/2022 | APPLICANT |
| Plan Check Approved | 12/15/2022 | SEAN SHAHMIRI |
| Issued | 12/15/2022 | APPLICANT |
| CofO in Progress | 3/13/2024 | KRISTEN BEVERIDGE |
| Permit Finaled | 5/17/2024 | DANIEL ORRANTE |
| CofO Issued | 5/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/19/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 9/20/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 11/21/2022 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 11/21/2022 | CARLOS AGUILERA |
| Green Code | Cleared | 12/15/2022 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/24/2023 | Approved | KRISTEN CAUSEY |
| PLUMBING-Rough | 1/24/2023 | Partial Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 2/17/2023 | Conditional Approval | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 2/17/2023 | Approved | KRISTEN CAUSEY |
| Green Building Rough | 2/17/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| HVAC-Rough | 2/17/2023 | Approved | KRISTEN CAUSEY |
| PLUMBING-Rough | 2/17/2023 | Approved | KRISTEN CAUSEY |
| Verify Sprinkler Sign Off | 2/17/2023 | Partial Inspection | KRISTEN CAUSEY |
| Deputy Wood Construction | 2/21/2023 | Conditional Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/24/2023 | Partial Inspection | JUSTIN HAWLEY |
| Deputy Wood Construction | 2/24/2023 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 2/24/2023 | Approved | JUSTIN HAWLEY |
| Insulation | 2/24/2023 | Corrections Issued | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 2/24/2023 | Partial Inspection | JUSTIN HAWLEY |
| Drywall Nailing | 3/7/2023 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 5/11/2023 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/4/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 12/4/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 12/4/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 12/4/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Final | 12/4/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 12/4/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 12/4/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 12/4/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 12/4/2023 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 12/4/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 1/4/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Green Building Final | 1/4/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Service/Power Release | 1/4/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Final | 3/12/2024 | OK to Issue CofO | KRISTEN CAUSEY |
| Green Building Final | 3/12/2024 | Approved | KRISTEN CAUSEY |
| Service/Power Release | 3/12/2024 | Approved | KRISTEN CAUSEY |