7520 N JUMILLA AVE 91306
Certificate Information: 7520 N JUMILLA AVE 91306
- Application / Permit
- 21010-20000-06112
- Plan Check / Job No.
- B21VN16214
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New Detached ADU 19'x19'
- Permit Issued
- Issued on 7/25/2022
- Issuing Office
- Current Status
- CofO Issued on 11/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | JOE VO |
| Corrections Issued | 11/25/2021 | JOE VO |
| Applicant returned to address corrections | 1/4/2022 | JOE VO |
| Applicant returned to address corrections | 2/16/2022 | JOE VO |
| Applicant returned to address corrections | 2/27/2022 | JOE VO |
| Plan Check Approved | 4/19/2022 | JOE VO |
| Issued | 7/25/2022 | APPLICANT |
| CofO in Progress | 9/6/2023 | ALEXANDER HANDY |
| Permit Finaled | 11/27/2023 | JOHN JANSON |
| CofO Issued | 11/27/2023 | JOHN JANSON |
| Permit Finaled | 11/27/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/3/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/3/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/4/2022 | DWAYNE LAURENT |
| Construction near power lines | Cleared | 4/13/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/14/2022 | Not Ready for Inspection | ALEXANDER HANDY |
| Footing/Foundation/Slab | 12/14/2022 | Approved | ALEXANDER HANDY |
| Green Building Rough | 12/14/2022 | Not Ready for Inspection | ALEXANDER HANDY |
| Pre-Inspection | 12/14/2022 | Approved | ALEXANDER HANDY |
| Reinforced Concrete Frame | 12/14/2022 | Not Ready for Inspection | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 12/14/2022 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 1/26/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 1/26/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Rough | 1/26/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 1/26/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 2/3/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 2/3/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 2/3/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 2/3/2023 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 2/3/2023 | Corrections Issued | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 2/3/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 2/8/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 2/8/2023 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 3/8/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Rough | 3/8/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 3/8/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 3/8/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 3/8/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Wood Frame | 3/8/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 3/10/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 3/10/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 3/22/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Rough | 3/22/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Insulation | 3/22/2023 | Corrections Issued | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 3/22/2023 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 4/3/2023 | Approved | VINCENT HANLEY |
| Pre-Inspection | 4/3/2023 | Partial Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Final | 4/27/2023 | Corrections Issued | ALEXANDER HANDY |
| Final | 5/5/2023 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 5/5/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 5/5/2023 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 5/5/2023 | SGSOV Not Required | JOHN KIDWELL |
| Smoke Detectors | 5/5/2023 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 5/12/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 7/7/2023 | Partial Approval | HORACE FULTZ |
| Final | 7/7/2023 | Not Ready for Inspection | HORACE FULTZ |
| Green Building Final | 7/7/2023 | Approved | HORACE FULTZ |
| Service/Power Release | 7/7/2023 | Not Ready for Inspection | HORACE FULTZ |
| BUILDING-Rough-Frame | 7/28/2023 | Corrections Issued | ALEXANDER HANDY |
| Final | 7/28/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Service/Power Release | 7/28/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 9/5/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 9/5/2023 | Approved | ALEXANDER HANDY |
| Final | 9/5/2023 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 9/5/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 9/5/2023 | Approved | ALEXANDER HANDY |
| Service/Power Release | 9/5/2023 | Approved | ALEXANDER HANDY |