13381 W OSBORNE ST 91331
Certificate Information: 13381 W OSBORNE ST 91331
- Application / Permit
- 21010-20000-06099
- Plan Check / Job No.
- B21VN16195
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 32'-8" X 38'-6" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/27/2022
- Issuing Office
- Current Status
- CofO Issued on 7/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | RAPHAEL ROSAS |
| Corrections Issued | 12/14/2021 | RAPHAEL ROSAS |
| Quality Review Completed | 12/16/2021 | STEVEN KIM |
| Building Plans Picked Up | 12/16/2021 | APPLICANT |
| Plan Check Approved | 4/21/2022 | RAPHAEL ROSAS |
| Issued | 4/27/2022 | APPLICANT |
| CofO in Progress | 7/28/2022 | MICHEL ABAJAN |
| Permit Finaled | 7/29/2022 | DANIEL ORRANTE |
| CofO Issued | 7/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/20/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 3/2/2022 | NADER ISKANDER |
| Low Impact Development | Cleared | 3/22/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 3/22/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/24/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/6/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/12/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/1/2022 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/1/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 6/1/2022 | Partial Inspection | MICHEL ABAJAN |
| MERV13>=Rough | 6/1/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/1/2022 | Partial Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 6/1/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/14/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/14/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 6/14/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/14/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/14/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 6/16/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/22/2022 | Approved | MICHEL ABAJAN |
| Shower Pan | 6/22/2022 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 6/29/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 7/15/2022 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 7/20/2022 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/28/2022 | Approved | MICHEL ABAJAN |
| Final | 7/28/2022 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 7/28/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/28/2022 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 7/28/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/28/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/28/2022 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 7/28/2022 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/28/2022 | Approved | MICHEL ABAJAN |