8114 N MAYNARD AVE 91304
Certificate Information: 8114 N MAYNARD AVE 91304
- Application / Permit
- 21010-20000-06096
- Plan Check / Job No.
- B21VN16175
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30'-5" X 36' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d). ALL WORK PER WFPP
- Permit Issued
- Issued on 9/28/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2021 | SERGIO MUNIZ |
| Corrections Issued | 12/4/2021 | SERGIO MUNIZ |
| Building Plans Picked Up | 12/8/2021 | APPLICANT |
| Plan Check Approved | 9/28/2022 | SERGIO MUNIZ |
| Issued | 9/28/2022 | APPLICANT |
| CofO in Progress | 11/4/2025 | HENRY KIM |
| Permit Finaled | 11/6/2025 | MICHAEL PELHAM |
| CofO Issued | 11/6/2025 | MICHAEL PELHAM |
| Permit Finaled | 11/6/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 12/10/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/10/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 2/17/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 8/9/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/15/2022 | COLIN LOREDO |
| Construction near power lines | Cleared | 9/9/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/24/2022 | Approved | JEFFREY PARD |
| Sewer | 10/24/2022 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 11/2/2022 | Approved | CHRIS CHRISTENSEN |
| Reinforced Concrete Frame | 11/2/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/8/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 12/8/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 12/8/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 12/8/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/16/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/29/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 12/29/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 12/29/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/13/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 1/13/2023 | Approved | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 1/13/2023 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 1/13/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 1/13/2023 | Approved | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 1/19/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 1/19/2023 | Approved | CHRIS CHRISTENSEN |
| Insulation | 1/24/2023 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 1/27/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 1/31/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Final | 3/23/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 3/23/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 3/23/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 3/23/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 3/23/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 4/12/2023 | Approved | HORACE FULTZ |
| Final | 4/12/2023 | Conditional Approval | HORACE FULTZ |
| Green Building Final | 4/12/2023 | Approved | HORACE FULTZ |
| HVAC-Final | 4/12/2023 | Approved | HORACE FULTZ |
| PLUMBING-Final | 4/12/2023 | Approved | HORACE FULTZ |
| Pre-Inspection | 4/12/2023 | Partial Inspection | JUSTIN HAWLEY |
| Service/Power Release | 4/12/2023 | Approved | HORACE FULTZ |
| Final | 11/4/2025 | OK to Issue CofO | HENRY KIM |