8045 N DARBY AVE 1-2 91335

Certificate Information: 8045 N DARBY AVE 1-2 91335

Application / Permit
21010-20000-06067
Plan Check / Job No.
B21VN16136
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. NEW ADDITION AT REAR TO (E) SINGLE FAMILY DWELLING WITH (E) ATTACHED JADU.
Permit Issued
Issued on 1/18/2022
Issuing Office
Current Status
CofO Issued on 5/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/23/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 KEVIN MORALES
Corrections Issued 11/25/2021 KEVIN MORALES
Applicant returned to address corrections 12/2/2021 KEVIN MORALES
Applicant returned to address corrections 1/5/2022 KEVIN MORALES
Plan Check Approved 1/10/2022 KEVIN MORALES
Issued 1/18/2022 APPLICANT
CofO in Progress 5/17/2022 VINCENT HANLEY
Permit Finaled 5/17/2022 MICHAEL SMITH
CofO Issued 5/17/2022 MICHAEL SMITH
Permit Finaled 5/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/29/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/29/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/30/2021 CARLOS AGUILERA
Sewer availability Cleared 11/30/2021 CARLOS AGUILERA

Contact Information

Contractor D H R Builders Inc; Lic. No.: 1054047-B 18336 DELANO STREET      TARZANA, CA 91335
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/1/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/9/2022 Partial Approval VINCENT HANLEY
Sewer 2/9/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/24/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 2/24/2022 Approved VINCENT HANLEY
Green Building Rough 2/24/2022 Approved VINCENT HANLEY
HVAC-Rough 2/24/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/24/2022 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 2/24/2022 Approved VINCENT HANLEY
Shower Pan 2/24/2022 Approved VINCENT HANLEY
Insulation 3/3/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/3/2022 Approved VINCENT HANLEY
Drywall Nailing 3/9/2022 Approved JESUS PINEDA
ELECTRICAL-Final 4/27/2022 Corrections Issued VINCENT HANLEY
Final 4/27/2022 Corrections Issued VINCENT HANLEY
HVAC-Final 4/27/2022 Corrections Issued VINCENT HANLEY
PLUMBING-Final 4/27/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/27/2022 SGSOV Approved VINCENT HANLEY
Service/Power Release 4/27/2022 Corrections Issued VINCENT HANLEY
Smoke Detectors 4/27/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 5/5/2022 Approved VINCENT HANLEY
Final 5/5/2022 Corrections Issued VINCENT HANLEY
HVAC-Final 5/5/2022 Approved VINCENT HANLEY
PLUMBING-Final 5/5/2022 Approved VINCENT HANLEY
Service/Power Release 5/5/2022 Approved VINCENT HANLEY
Final 5/17/2022 OK to Issue CofO VINCENT HANLEY