3935 N RHODES AVE 91604
Certificate Information: 3935 N RHODES AVE 91604
- Application / Permit
- 21010-20000-06049
- Plan Check / Job No.
- B21VN16084
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (38'-0"x74'-9"), 5953 SQFT 2 STORY SINGLE FAMILY DWELLING W/1959 SQFT BASEMENT AND SHORING W/NFPA 13D SPRINKLERS THROUGHOUT SEE COMMENTS.
- Permit Issued
- Issued on 12/21/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2021 | PETER MOSESIAN |
| Corrections Issued | 12/25/2021 | PETER MOSESIAN |
| Quality Review Completed | 1/6/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 1/19/2022 | APPLICANT |
| Applicant returned to address corrections | 6/30/2022 | PETER MOSESIAN |
| Plan Check Approved | 7/25/2022 | PETER MOSESIAN |
| Issued | 12/21/2022 | APPLICANT |
| CofO in Progress | 5/2/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 5/23/2025 | RUBEN SALAS |
| CofO Issued | 5/23/2025 | RUBEN SALAS |
| Permit Finaled | 5/23/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/3/2022 | CARLOS AGUILERA |
| City Hist. Cultural Monument | Cleared | 2/8/2022 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 2/8/2022 | LAMBERT GIESSINGER |
| Hydrant and Access approval | Cleared | 2/25/2022 | LAURINDA MEADE |
| ZI | Cleared | 3/15/2022 | LAUREN PADICK |
| Low Impact Development | Cleared | 5/5/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/9/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/16/2023 | Approved | CHRISTOPHE COCHRAN |
| Piling/Pier/Caisson | 2/16/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Reinf. Concrete | 2/21/2023 | Conditional Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 5/17/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Underground Mechanical | 5/17/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Underground Mechanical | 5/22/2023 | Partial Approval | JOHN COLEMAN |
| Footing/Foundation/Slab | 6/23/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Underground Mechanical | 6/23/2023 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 7/21/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Shotcrete | 7/24/2023 | Conditional Approval | JUAN VALENZUELA |
| Wood Frame | 8/29/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2023 | Conditional Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 9/26/2023 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/26/2023 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/29/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 1/3/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Sewer | 1/3/2024 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Corrections Issued | JOHN COLEMAN |
| HVAC-Rough | 1/16/2024 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 1/16/2024 | Partial Approval | JOHN COLEMAN |
| ELECTRICAL-Rough | 1/17/2024 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2024 | Approved | CHRISTOPHE COCHRAN |
| Gas Test | 1/24/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 1/24/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 2/1/2024 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 2/1/2024 | Approved | CHRISTOPHE COCHRAN |
| Structural Steel Frame | 2/1/2024 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 2/1/2024 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 2/1/2024 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 2/26/2024 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 3/20/2024 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 3/22/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 5/6/2024 | Approved | CHRISTOPHER ROJAS |
| Gas Test | 6/17/2024 | Approved | CHRISTOPHE COCHRAN |
| Final | 1/3/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 1/3/2025 | Approved | CHRISTOPHE COCHRAN |
| Gas Test | 1/3/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Final | 1/3/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 1/3/2025 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 1/3/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 1/3/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 2/11/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 2/11/2025 | Approved | JACK KARGODORIAN |
| Service/Power Release | 2/11/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 4/29/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 4/29/2025 | Approved | CHRISTOPHE COCHRAN |