6259 N BUFFALO AVE 91401

Certificate Information: 6259 N BUFFALO AVE 91401

Application / Permit
21010-20000-06038
Plan Check / Job No.
B21VN16067
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d) "The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy."
Permit Issued
Issued on 7/8/2022
Issuing Office
Current Status
Issued on 7/8/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/22/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 DANIEL YIP
Corrections Issued 12/14/2021 DANIEL YIP
Quality Review Completed 12/16/2021 PRANITA SHAH
Applicant returned to address corrections 1/26/2022 DANIEL YIP
Applicant returned to address corrections 2/16/2022 DANIEL YIP
Applicant returned to address corrections 6/13/2022 DANIEL YIP
Plan Check Approved 6/23/2022 DANIEL YIP
Issued 7/8/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/18/2022 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 1/18/2022 AMIR KASHFI
Sewer availability Cleared 1/18/2022 AMIR KASHFI
Roof/Waste drainage to street Cleared 6/22/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: NA56881       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/12/2023 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Rough 1/12/2023 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 1/17/2023 Corrections Issued KIRK SANDERS
Excavation/Setback/Form/Re-Bar 1/23/2023 Approved DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 2/17/2023 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Approved KIRK SANDERS
Green Building Rough 2/23/2023 Corrections Issued KIRK SANDERS
Light Gage Steel Frame 2/23/2023 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 2/23/2023 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 3/3/2023 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 3/3/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 3/3/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 3/7/2023 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Approved KIRK SANDERS
Gas Test 3/7/2023 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 3/7/2023 Approved KIRK SANDERS
PLUMBING-Rough 3/7/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 3/13/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 3/13/2023 Approved KIRK SANDERS
Green Building Rough 3/13/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 3/13/2023 Partial Approval KIRK SANDERS
Shower Pan 3/13/2023 Approved KIRK SANDERS
Verify Sprinkler Sign Off 3/13/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 4/4/2023 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 5/2/2023 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 5/2/2023 Approved KIRK SANDERS
Verify Sprinkler Sign Off 5/2/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 5/8/2023 Corrections Issued KIRK SANDERS
Insulation 5/8/2023 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 5/18/2023 Approved KIRK SANDERS
Insulation 5/22/2023 Approved KIRK SANDERS
Drywall Nailing 5/26/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 5/26/2023 Approved KIRK SANDERS
Footing/Foundation/Slab 6/26/2025 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 6/26/2025 SGSOV Not Ready OGANES TARAKHCHYAN
Service/Power Release 7/10/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Final 7/21/2025 No Access for Inspection GAREN HAYRAPETYAN
Green Building Final 7/21/2025 No Access for Inspection GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 7/21/2025 SGSOV Not Ready GAREN HAYRAPETYAN
Service/Power Release 7/21/2025 No Access for Inspection GAREN HAYRAPETYAN
Smoke Detectors 7/21/2025 No Access for Inspection GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Not Ready OGANES TARAKHCHYAN
Final 8/1/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 8/1/2025 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/1/2025 SGSOV Not Ready OGANES TARAKHCHYAN
Service/Power Release 8/1/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Final 11/21/2025 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 11/21/2025 SGSOV Approved OGANES TARAKHCHYAN
Final 12/2/2025 Not Ready for Inspection WAYNE REGESTER
Service/Power Release 12/2/2025 Not Ready for Inspection WAYNE REGESTER
Smoke Detectors 12/2/2025 Not Ready for Inspection WAYNE REGESTER
Final 12/29/2025 Not Ready for Inspection WAYNE REGESTER
Service/Power Release 12/29/2025 Not Ready for Inspection WAYNE REGESTER
Smoke Detectors 12/29/2025 Not Ready for Inspection WAYNE REGESTER
Final 1/20/2026 No Access for Inspection JOSE AVILA
Service/Power Release 1/20/2026 No Access for Inspection JOSE AVILA
Smoke Detectors 1/20/2026 No Access for Inspection JOSE AVILA
Final 1/29/2026 Partial Approval WAYNE REGESTER
Service/Power Release 1/29/2026 Approved WAYNE REGESTER
Smoke Detectors 1/29/2026 Approved WAYNE REGESTER
Special/Order Compliance 4/21/2026 Corrections Issued RAUL OLAGI