725 1/2 E 55TH ST 90011

Certificate Information: 725 1/2 E 55TH ST 90011

Application / Permit
21010-20000-05987
Plan Check / Job No.
B21VN15862
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached 1-story ADU per ordinance 186,481.
Permit Issued
Issued on 4/29/2022
Issuing Office
Current Status
Permit Finaled on 1/4/2023
Certificate of Occupancy
Permit Finaled More Information

Permit Application Status History

Submitted 11/17/2021 APPLICANT
Assigned to Plan Check Engineer 11/22/2021 HELEN NGUYEN
Corrections Issued 11/23/2021 HELEN NGUYEN
Applicant returned to address corrections 1/24/2022 HELEN NGUYEN
Applicant returned to address corrections 2/4/2022 HELEN NGUYEN
Applicant returned to address corrections 3/1/2022 HELEN NGUYEN
Applicant returned to address corrections 4/15/2022 HELEN NGUYEN
Plan Check Approved 4/29/2022 HELEN NGUYEN
Issued 4/29/2022 APPLICANT
CofO in Progress 12/28/2022 RUBEN SALAS
Permit Finaled 1/4/2023 DEROLD HAUFF
CofO Issued 1/4/2023 DEROLD HAUFF
Permit Finaled 1/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/12/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/9/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 2/9/2022 JEANETTE VONG
Sewer availability Cleared 2/9/2022 JEANETTE VONG
Hydrant and Access approval Cleared 3/19/2022 DWIGHT SANKEY

Contact Information

Contractor Owner-Builder       ,
Engineer Rincon,, Daniela A; Lic. No.: C90392 7SS S BIXEL #942      LOS ANGELES, CA 90017

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/6/2022 Approved JOAQUIN GREENOUGH
Pre-Inspection 6/1/2022 Corrections Issued JOAQUIN GREENOUGH
Underground Mechanical 6/15/2022 Partial Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 6/21/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/21/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 6/27/2022 Approved JOAQUIN GREENOUGH
Insulation 7/5/2022 Not Ready for Inspection HORACE FULTZ
Wood Frame 7/5/2022 Partial Approval HORACE FULTZ
Insulation 7/8/2022 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 7/11/2022 Partial Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 8/17/2022 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/22/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 8/22/2022 Conditional Approval JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 8/22/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 9/2/2022 Not Ready for Inspection SHAVONNE ESPINOZA
HVAC-Rough 9/2/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Insulation 9/2/2022 Not Ready for Inspection SHAVONNE ESPINOZA
PLUMBING-Rough 9/2/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Rough-Elec/Plmb/HVAC 9/2/2022 Not Ready for Inspection SHAVONNE ESPINOZA
ELECTRICAL-Rough 9/7/2022 Conditional Approval HORACE FULTZ
HVAC-Rough 9/7/2022 Not Ready for Inspection HORACE FULTZ
Insulation 9/7/2022 Conditional Approval HORACE FULTZ
Interior/Exterior Lathing 9/7/2022 Partial Approval HORACE FULTZ
PLUMBING-Rough 9/7/2022 Approved HORACE FULTZ
ELECTRICAL-Rough 9/19/2022 Partial Approval RYAN SALAZAR
HVAC-Rough 9/19/2022 Approved RYAN SALAZAR
Insulation 9/19/2022 Approved RYAN SALAZAR
Drywall Nailing 9/21/2022 Corrections Issued SHAVONNE ESPINOZA
Drywall Nailing 9/23/2022 Approved RUBEN SALAS
ELECTRICAL-Rough 9/23/2022 Approved RUBEN SALAS
ELECTRICAL-Final 9/27/2022 Not Ready for Inspection HORACE FULTZ
ELECTRICAL-Rough 9/27/2022 Corrections Issued HORACE FULTZ
Rough-Elec/Plmb/HVAC 9/27/2022 Not Ready for Inspection HORACE FULTZ
Pre-Inspection 9/29/2022 Approved STUART CHAPMAN
Special/Order Compliance 9/29/2022 Approved SHAVONNE ESPINOZA
ELECTRICAL-Rough 10/17/2022 Corrections Issued SHAVONNE ESPINOZA
Interior/Exterior Lathing 10/17/2022 Corrections Issued SHAVONNE ESPINOZA
Interior/Exterior Lathing 10/19/2022 Approved HORACE FULTZ
ELECTRICAL-Final 10/31/2022 Approved RUBEN SALAS
HVAC-Final 10/31/2022 Approved RUBEN SALAS
PLUMBING-Final 10/31/2022 Approved RUBEN SALAS
Service/Power Release 10/31/2022 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Final 12/13/2022 Approved RUBEN SALAS
Final 12/13/2022 Corrections Issued RUBEN SALAS
Footing/Foundation/Slab 12/13/2022 Approved RUBEN SALAS
HVAC-Final 12/13/2022 Approved RUBEN SALAS
PLUMBING-Final 12/13/2022 Approved RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 12/13/2022 SGSOV Approved RUBEN SALAS
Service/Power Release 12/13/2022 Approved RUBEN SALAS
Smoke Detectors 12/13/2022 Approved RUBEN SALAS
Final 12/27/2022 OK to Issue CofO RUBEN SALAS