3670 W 61ST ST 90043

Certificate Information: 3670 W 61ST ST 90043

Application / Permit
21010-20000-05983
Plan Check / Job No.
B21VN15842
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d)
Permit Issued
Issued on 3/31/2022
Issuing Office
Current Status
CofO Issued on 6/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 NILOOFAR MEHRAIN
Corrections Issued 12/21/2021 NILOOFAR MEHRAIN
Quality Review Completed 12/23/2021 STEVEN KIM
Building Plans Picked Up 12/23/2021 APPLICANT
Plan Check Approved 3/15/2022 NILOOFAR MEHRAIN
Issued 3/31/2022 APPLICANT
CofO in Progress 5/26/2023 ENRIQUE MIRELES
CofO in Progress 5/26/2023 ENRIQUE MIRELES
Permit Finaled 6/1/2023 DEROLD HAUFF
CofO Issued 6/1/2023 DEROLD HAUFF
Permit Finaled 6/1/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/28/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/4/2022 CELINA MORENO
Sewer availability Cleared 1/4/2022 CELINA MORENO
Low Impact Development Cleared 2/2/2022 LONDY ALVARADO
Hydrant and Access approval Cleared 3/4/2022 DWIGHT SANKEY
Roof/Waste drainage to street Cleared 3/4/2022 CELINA MORENO

Contact Information

Contractor Stash Builders Inc; Lic. No.: 1066308-B 5811 EDMUND AVENUE      LA CRESCENTA, CA 91214
Engineer Abedian,, Vanik; Lic. No.: S5323 2906 JOLLEY DR      BURBANK, CA 91504

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/22/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 5/5/2022 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 5/10/2022 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 5/24/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 7/13/2022 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 7/13/2022 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 7/13/2022 Approved ENRIQUE MIRELES
HVAC-Rough 7/26/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 7/26/2022 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 8/15/2022 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 8/15/2022 Approved ENRIQUE MIRELES
Green Building Rough 8/15/2022 Approved ENRIQUE MIRELES
HVAC-Rough 8/15/2022 Partial Approval ENRIQUE MIRELES
PLUMBING-Rough 8/15/2022 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 8/15/2022 Approved ENRIQUE MIRELES
Wood Frame 8/15/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 8/17/2022 Approved ENRIQUE MIRELES
HVAC-Rough 8/17/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 8/17/2022 Approved ENRIQUE MIRELES
Wood Frame 8/17/2022 Approved ENRIQUE MIRELES
Insulation 8/29/2022 Approved ENRIQUE MIRELES
Drywall Nailing 9/16/2022 Approved ENRIQUE MIRELES
Shower Pan 9/16/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 9/23/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 10/25/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 11/2/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/30/2022 Approved ENRIQUE MIRELES
Underground Mechanical 1/24/2023 Approved ENRIQUE MIRELES
Sewer 2/8/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 3/24/2023 Approved ENRIQUE MIRELES
Final 3/24/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 3/24/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/24/2023 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 3/24/2023 Approved ENRIQUE MIRELES
Smoke Detectors 3/24/2023 Approved ENRIQUE MIRELES
Final 4/13/2023 Corrections Issued ENRIQUE MIRELES
Final 5/19/2023 OK to Issue CofO ENRIQUE MIRELES