19640 W REDWING ST 91356

Certificate Information: 19640 W REDWING ST 91356

Application / Permit
21010-20000-05958
Plan Check / Job No.
B21VN15737
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED (33'-10"x30'-11"), 764 SQFT ADU W/NFPA 13D SPRINKLERS THROUGHOUT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
Permit Issued
Issued on 5/25/2022
Issuing Office
Current Status
CofO Issued on 6/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 PETER MOSESIAN
Corrections Issued 12/23/2021 PETER MOSESIAN
Quality Review Completed 12/23/2021 OMID HEDAYAT
Building Plans Picked Up 12/27/2021 APPLICANT
Plan Check Approved 5/2/2022 PETER MOSESIAN
Issued 5/25/2022 APPLICANT
CofO in Progress 6/14/2023 SEAN WIRCH
Permit Finaled 6/20/2023 JOHN JANSON
CofO Issued 6/20/2023 JOHN JANSON
Permit Finaled 6/20/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/27/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/27/2021 CARLOS AGUILERA
Sewer availability Cleared 12/27/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 3/11/2022 CINDY JOSSELYN
Construction near power lines Cleared 3/13/2022 RIDWAN HARDY
Low Impact Development Cleared 4/15/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 4/15/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/17/2022 Corrections Issued DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 8/11/2022 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 9/9/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 10/19/2022 Approved DAVID SANDOVAL
ELECTRICAL-Rough 10/19/2022 Approved DAVID SANDOVAL
Green Building Rough 10/19/2022 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 10/19/2022 Approved DAVID SANDOVAL
MERV13>=Rough 10/19/2022 Approved DAVID SANDOVAL
PLUMBING-Rough 10/19/2022 Approved DAVID SANDOVAL
Rough-Elec/Plmb/HVAC 10/19/2022 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 10/19/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 11/10/2022 Partial Approval DAVID SANDOVAL
Drywall Nailing 11/16/2022 Approved DAVID SANDOVAL
Green Building Rough 11/16/2022 Approved DAVID SANDOVAL
Gas Test 3/21/2023 Approved DAVID SANDOVAL
ELECTRICAL-Final 5/1/2023 Approved SEAN HAUPT
Final 5/1/2023 Corrections Issued SEAN HAUPT
Green Building Final 5/1/2023 Not Ready for Inspection SEAN HAUPT
HVAC-Final 5/1/2023 Approved SEAN HAUPT
PLUMBING-Final 5/1/2023 Approved SEAN HAUPT
Service/Power Release 5/1/2023 Not Ready for Inspection SEAN HAUPT
Smoke Detectors 5/1/2023 Approved SEAN HAUPT
Final 6/6/2023 No Access for Inspection VINCENT HANLEY
Footing/Foundation/Slab 6/6/2023 No Access for Inspection VINCENT HANLEY
Green Building Final 6/6/2023 No Access for Inspection VINCENT HANLEY
MERV13>=Final 6/6/2023 No Access for Inspection VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/6/2023 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 6/6/2023 No Access for Inspection VINCENT HANLEY
Final 6/15/2023 OK to Issue CofO SEAN WIRCH
Footing/Foundation/Slab 6/15/2023 Approved SEAN WIRCH
Green Building Final 6/15/2023 Approved SEAN WIRCH
MERV13>=Final 6/15/2023 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 6/15/2023 SGSOV Approved SEAN WIRCH
Service/Power Release 6/15/2023 Approved SEAN WIRCH