8912 1/2 N HASKELL AVE 91343
Certificate Information: 8912 1/2 N HASKELL AVE 91343
- Application / Permit
- 21010-20000-05956
- Plan Check / Job No.
- B21VN15733
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 24'-0" x 26'-0" DETACHED TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 1/31/2024
- Issuing Office
- Valley
- Current Status
- Issued on 1/31/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 12/20/2021 | SARKIS HARABEDIAN |
| Quality Review Completed | 12/23/2021 | STEVEN KIM |
| Applicant returned to address corrections | 3/11/2022 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 4/14/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 5/2/2022 | APPLICANT |
| Plan Check Approved | 9/1/2023 | SARKIS HARABEDIAN |
| Issued | 1/31/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/7/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 8/7/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 8/18/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/13/2024 | No Access for Inspection | RAUL OLAGI |
| Pre-Inspection | 2/15/2024 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 10/22/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Special/Order Compliance | 10/22/2024 | Partial Inspection | RAUL OLAGI |
| PLUMBING-Rough | 11/1/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 11/25/2024 | Partial Approval | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 8/20/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 10/15/2025 | Approved | GAREN HAYRAPETYAN |
| Deputy Wood Construction | 11/3/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/25/2026 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 2/25/2026 | Partial Inspection | MISAEL ESPARZA |
| Green Building Rough | 2/25/2026 | Partial Inspection | MISAEL ESPARZA |
| HVAC-Rough | 2/25/2026 | Partial Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 2/25/2026 | Partial Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 2/25/2026 | Partial Inspection | MISAEL ESPARZA |
| Sewer | 2/25/2026 | Partial Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 2/25/2026 | Partial Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 4/21/2026 | Corrections Issued | JOSE AVILA |