8912 1/2 N HASKELL AVE 91343

Certificate Information: 8912 1/2 N HASKELL AVE 91343

Application / Permit
21010-20000-05956
Plan Check / Job No.
B21VN15733
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 24'-0" x 26'-0" DETACHED TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 1/31/2024
Issuing Office
Valley
Current Status
Issued on 1/31/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/17/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 SARKIS HARABEDIAN
Corrections Issued 12/20/2021 SARKIS HARABEDIAN
Quality Review Completed 12/23/2021 STEVEN KIM
Applicant returned to address corrections 3/11/2022 SARKIS HARABEDIAN
Applicant returned to address corrections 4/14/2022 SARKIS HARABEDIAN
Building Plans Picked Up 5/2/2022 APPLICANT
Plan Check Approved 9/1/2023 SARKIS HARABEDIAN
Issued 1/31/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/21/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 2/7/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 2/7/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 8/7/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 8/18/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/13/2024 No Access for Inspection RAUL OLAGI
Pre-Inspection 2/15/2024 Approved RAUL OLAGI
PLUMBING-Rough 10/22/2024 Corrections Issued SALVADOR MARTINEZ
Special/Order Compliance 10/22/2024 Partial Inspection RAUL OLAGI
PLUMBING-Rough 11/1/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 11/25/2024 Partial Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 8/20/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 10/15/2025 Approved GAREN HAYRAPETYAN
Deputy Wood Construction 11/3/2025 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 2/25/2026 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 2/25/2026 Partial Inspection MISAEL ESPARZA
Green Building Rough 2/25/2026 Partial Inspection MISAEL ESPARZA
HVAC-Rough 2/25/2026 Partial Inspection MISAEL ESPARZA
MERV13>=Rough 2/25/2026 Partial Inspection MISAEL ESPARZA
PLUMBING-Rough 2/25/2026 Partial Inspection MISAEL ESPARZA
Sewer 2/25/2026 Partial Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 2/25/2026 Partial Inspection MISAEL ESPARZA
PLUMBING-Rough 4/21/2026 Corrections Issued JOSE AVILA