7723 N NESTLE AVE 91335
Certificate Information: 7723 N NESTLE AVE 91335
- Application / Permit
- 21010-20000-05950
- Plan Check / Job No.
- B21VN15703
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW( 32'-3"x 21'-0") TWO STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 4/7/2022
- Issuing Office
- Current Status
- CofO Issued on 6/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | TROY DEGUZMAN |
| Corrections Issued | 12/22/2021 | TROY DEGUZMAN |
| Quality Review Completed | 12/29/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 12/30/2021 | APPLICANT |
| Plan Check Approved | 4/7/2022 | TROY DEGUZMAN |
| Issued | 4/7/2022 | APPLICANT |
| CofO in Progress | 6/15/2022 | VINCENT HANLEY |
| Permit Finaled | 6/30/2022 | MICHAEL SMITH |
| CofO Issued | 6/30/2022 | MICHAEL SMITH |
| Permit Finaled | 6/30/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/19/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 3/8/2022 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 3/8/2022 | LARRY REDDEN |
| Low Impact Development | Cleared | 3/15/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 3/17/2022 | CARLOS AGUILERA |
| Green Code | Cleared | 3/30/2022 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/13/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/13/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/13/2022 | Partial Approval | VINCENT HANLEY |
| Sewer | 4/13/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/15/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/20/2022 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2022 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 4/20/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 4/20/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2022 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 5/4/2022 | Approved | VINCENT HANLEY |
| Underground Mechanical | 5/4/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/6/2022 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 5/6/2022 | Approved | VINCENT HANLEY |
| Insulation | 5/6/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/6/2022 | Partial Approval | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 5/6/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Drywall Nailing | 5/10/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 5/10/2022 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 6/3/2022 | Approved | VINCENT HANLEY |
| Final | 6/3/2022 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 6/3/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/3/2022 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 6/3/2022 | Approved | VINCENT HANLEY |
| Smoke Detectors | 6/3/2022 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 6/3/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Final | 6/15/2022 | OK to Issue CofO | VINCENT HANLEY |