5926 N TROOST AVE 91601
Certificate Information: 5926 N TROOST AVE 91601
- Application / Permit
- 21010-20000-05925
- Plan Check / Job No.
- B21VN15663
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 30' X 40' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/16/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | RAPHAEL ROSAS |
| Corrections Issued | 11/25/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 11/29/2021 | APPLICANT |
| Applicant returned to address corrections | 12/6/2022 | MADISON ODELL |
| Plan Check Approved | 12/16/2022 | MADISON ODELL |
| Issued | 12/16/2022 | APPLICANT |
| CofO in Progress | 12/13/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 1/7/2025 | RUBEN SALAS |
| CofO Issued | 1/7/2025 | RUBEN SALAS |
| Permit Finaled | 1/7/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/29/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 9/29/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 10/11/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 10/18/2022 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 11/16/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/7/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 8/18/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 8/22/2023 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 8/24/2023 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 11/1/2023 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Rough | 11/1/2023 | Partial Approval | JOHN COLEMAN |
| Green Building Rough | 11/1/2023 | Partial Approval | JOHN COLEMAN |
| HVAC-Rough | 11/1/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 11/1/2023 | Approved | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 11/1/2023 | Partial Inspection | JOHN COLEMAN |
| Deputy Drilled-In Anchors | 11/27/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/28/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/28/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 11/28/2023 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 11/28/2023 | Approved | MICHEL ABAJAN |
| Insulation | 12/4/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 12/8/2023 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 12/8/2023 | Partial Approval | JUAN VALENZUELA |
| Final | 9/19/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 9/19/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 9/19/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 9/19/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| Service/Power Release | 9/19/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 9/19/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 9/30/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 9/30/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 9/30/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 10/4/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 10/4/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 10/4/2024 | Approved | CHRISTOPHER ROJAS |