15731 W HESBY ST 91403
Certificate Information: 15731 W HESBY ST 91403
- Application / Permit
- 21010-20000-05922
- Plan Check / Job No.
- B21VN15658
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 42' x 46'-4" IRR. SHAPED DETACHED REC.ROOM & PATIO COVER W/ AN ATT. SHOWER FOR (E) POOL AND HALF BATHROOM; ALL WORK PER ENGINEERING DESIGN; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 3/6/2023
- Issuing Office
- Metro
- Current Status
- Issued on 3/6/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | SEAN SHAHMIRI |
| Corrections Issued | 12/13/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 12/21/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 12/22/2021 | APPLICANT |
| Applicant returned to address corrections | 2/27/2023 | SEAN SHAHMIRI |
| Plan Check Approved | 3/2/2023 | SEAN SHAHMIRI |
| Issued | 3/6/2023 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 1/13/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/15/2022 | JOSE DUARTE-DIAZ |
| Construction within easement | Cleared | 3/15/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/14/2023 | LUIS LUVANO |
| Hydrant and Access approval | Cleared | 3/1/2023 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 3/2/2023 | CHRISTINE REUSCH |
| Public Works-Highway Ded. | Cleared | 3/2/2023 | CHRISTINE REUSCH |
| Public Works-Open Permits | Cleared | 3/2/2023 | CHRISTINE REUSCH |
| Public Works-Sewers | Cleared | 3/2/2023 | CHRISTINE REUSCH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abkarian,, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/26/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Pre-Inspection | 1/30/2024 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/8/2024 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 2/15/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/8/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2024 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2024 | Partial Approval | GEVORK IPCHYAN |
| Underground Mechanical | 7/3/2024 | Partial Approval | THOMAS FINNILA |
| Underground Mechanical | 7/11/2024 | Partial Approval | JEFFREY BULL |
| ELECTRICAL-Rough | 9/13/2024 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 9/13/2024 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 11/6/2024 | Not Ready for Inspection | SEAN WIRCH |
| Interior/Exterior Lathing | 1/28/2025 | No Access for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 1/30/2025 | Partial Approval | JOHN COLEMAN |
| BUILDING-Rough-Frame | 2/12/2025 | Corrections Issued | JOHN COLEMAN |
| BUILDING-Rough-Frame | 2/18/2025 | Conditional Approval | THOMAS FINNILA |
| Green Building Rough | 2/18/2025 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 2/18/2025 | Conditional Approval | THOMAS FINNILA |
| Insulation | 3/5/2025 | Conditional Approval | THOMAS FINNILA |
| Drywall Nailing | 3/25/2025 | Corrections Issued | MORRIS JACKSON |
| Drywall Nailing | 4/3/2025 | No Access for Inspection | THOMAS FINNILA |
| Drywall Nailing | 4/11/2025 | Partial Approval | HENRY KIM |
| Insulation | 4/11/2025 | Approved | HENRY KIM |
| Drywall Nailing | 5/6/2025 | Approved | JOHN COLEMAN |
| Shower Pan | 5/6/2025 | Approved | JOHN COLEMAN |
| Pre-Inspection | 7/8/2025 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 7/28/2025 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 8/6/2025 | Partial Approval | THOMAS FINNILA |