5262 N CLEON AVE 1-15 91601

Certificate Information: 5262 N CLEON AVE 1-15 91601

Application / Permit
21010-20000-05918
Plan Check / Job No.
B21VN15643
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 3-story with roof deck, Type VA, 15-unit (100% affordable) apartment using TOC Tier 4 incentives.
Permit Issued
Issued on 8/14/2024
Issuing Office
Current Status
CofO Issued on 5/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 RODOLFO ARIAS
Corrections Issued 11/21/2021 RODOLFO ARIAS
Quality Review Completed 11/23/2021 EUGENE BARBEAU
Applicant returned to address corrections 8/19/2022 RODOLFO ARIAS
Applicant returned to address corrections 10/6/2023 RODOLFO ARIAS
Applicant returned to address corrections 11/22/2023 RODOLFO ARIAS
Plan Check Approved 5/7/2024 RODOLFO ARIAS
Issued 8/14/2024 APPLICANT
CofO in Progress 5/27/2026 RICKEY JACKSON
Permit Finaled 5/27/2026 RICKEY JACKSON
CofO Issued 5/27/2026 RICKEY JACKSON
Permit Finaled 5/27/2026 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 11/24/2021 CARLOS AGUILERA
Highway dedication Cleared 11/24/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/30/2021 CARLOS AGUILERA
Sewer availability Cleared 12/1/2021 CARLOS AGUILERA
Trees in Parkway Cleared 2/23/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 3/11/2022 GREGORY HOERNER
Low Impact Development Cleared 5/23/2022 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 6/6/2022 CARLOS AGUILERA
CPC Cleared 8/30/2022 MIGUEL GAMBOA
Frnt yard landscape/Water mgmt Cleared 8/30/2022 MIGUEL GAMBOA
Opn space landscape/Water mgmt Cleared 8/30/2022 MIGUEL GAMBOA
Density Bonus 12.22.A.31 Cleared 11/1/2022 NICHOLAS KAWAZOE
Fire Marshal Fire Life Safety Cleared 1/10/2023 WILLIAM JOHNS
Green Code Cleared 2/8/2023 AARON COSTA
Building over 36-ft Cleared 4/28/2023 CALOSHA APPROVED
Construction near power lines Cleared 8/18/2023 RIDWAN HARDY
DAS Clearance Cleared 11/30/2023 RODOLFO ARIAS

Contact Information

Contractor Dotz Inc; Lic. No.: 1033830-B 15500 ERWIN STREET #1011      VAN NUYS, CA 91411
Engineer Parvini,, Mehdi; Lic. No.: C63186 1226 SOUZA DRIVE      EL DORADO HILLS, CA 95762
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/10/2024 Partial Inspection JOHN KITCKO
Pre-Inspection 9/10/2024 Partial Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 9/30/2024 Corrections Issued JOHN KITCKO
Wall Anchors 9/30/2024 Not Ready for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 10/3/2024 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 10/7/2024 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 10/8/2024 Conditional Approval CAMERON CHABAN
Deputy Wood Construction 11/8/2024 Conditional Approval JOHN KITCKO
Deputy Wood Construction 11/12/2024 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Corrections Issued JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 11/15/2024 Partial Approval JOHN KITCKO
Deputy Wood Construction 12/4/2024 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 12/5/2024 Partial Approval RAFAEL CORTES
Deputy Wood Construction 12/20/2024 Approved JOHN KITCKO
Deputy Wood Construction 12/20/2024 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 12/24/2024 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 1/3/2025 Not Ready for Inspection JOHN KITCKO
Wall Anchors 1/3/2025 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 1/10/2025 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 2/11/2025 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 2/18/2025 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 3/10/2025 Approved JOHN KITCKO
Insulation 3/28/2025 No Access for Inspection JOHN KITCKO
Insulation 4/2/2025 Partial Approval JOHN KITCKO
Drywall Nailing 4/15/2025 Partial Inspection JOHN KITCKO
Green Building Rough 5/8/2025 Not Ready for Inspection JOHN KITCKO
METHANE-Rough 5/8/2025 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 5/8/2025 Not Ready for Inspection JOHN KITCKO
Wood Frame 5/8/2025 Partial Approval JOHN KITCKO
Green Building Rough 7/10/2025 Not Ready for Inspection JOHN KITCKO
METHANE-Rough 7/10/2025 Approved JOHN KITCKO
Verify Sprinkler Sign Off 7/10/2025 Not Ready for Inspection JOHN KITCKO
Wood Frame 7/10/2025 Not Ready for Inspection JOHN KITCKO
Green Building Rough 7/14/2025 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 7/14/2025 Not Ready for Inspection JOHN KITCKO
Wood Frame 7/14/2025 Partial Inspection JOHN KITCKO
Green Building Rough 7/21/2025 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 7/21/2025 Not Ready for Inspection JOHN KITCKO
Wood Frame 7/21/2025 No Access for Inspection JOHN KITCKO
Green Building Rough 7/23/2025 Approved JOHN KITCKO
Insulation 7/23/2025 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 7/23/2025 Approved JOHN KITCKO
Wood Frame 7/23/2025 Approved JOHN KITCKO
Insulation 7/28/2025 Approved JOHN KITCKO
Drywall Nailing 8/4/2025 Not Ready for Inspection JOHN KITCKO
Special/Order Compliance 8/5/2025 Partial Approval JOHN KITCKO
Special/Order Compliance 9/25/2025 Partial Inspection JOHN KITCKO
Special/Order Compliance 2/23/2026 Not Ready for Inspection DEANDRE HOFFMAN
Final 4/14/2026 Not Ready for Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 4/14/2026 Approved DEANDRE HOFFMAN
Green Building Final 4/14/2026 Not Ready for Inspection DEANDRE HOFFMAN
METHANE-Barrier 4/14/2026 Approved DEANDRE HOFFMAN
METHANE-Subgrade 4/14/2026 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 4/14/2026 SGSOV Not Ready DEANDRE HOFFMAN
Smoke Detectors 4/14/2026 Partial Inspection DEANDRE HOFFMAN
Light Gage Steel Frame 4/29/2026 Approved DEANDRE HOFFMAN
Drywall Nailing 4/30/2026 Approved DEANDRE HOFFMAN
Final 5/5/2026 Not Ready for Inspection DEANDRE HOFFMAN
Green Building Final 5/5/2026 Not Ready for Inspection DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 5/5/2026 SGSOV Not Ready DEANDRE HOFFMAN
Smoke Detectors 5/5/2026 Not Ready for Inspection DEANDRE HOFFMAN
Final 5/8/2026 Corrections Issued DEANDRE HOFFMAN
Green Building Final 5/8/2026 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 5/8/2026 SGSOV Approved DEANDRE HOFFMAN
Smoke Detectors 5/8/2026 Approved DEANDRE HOFFMAN
Special/Order Compliance 5/12/2026 Partial Inspection DEANDRE HOFFMAN
Final 5/27/2026 OK to Issue CofO RICKEY JACKSON