13967 W BEAVER ST 91342
Certificate Information: 13967 W BEAVER ST 91342
- Application / Permit
- 21010-20000-05897
- Plan Check / Job No.
- B21VN15630
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SFD W/ATTACHED 2 CAR GARAGE (1-STORY)
- Permit Issued
- Issued on 4/1/2022
- Issuing Office
- Current Status
- CofO Issued on 10/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | CARLOS MONTES |
| Corrections Issued | 12/5/2021 | CARLOS MONTES |
| Quality Review Completed | 12/14/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 2/16/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 3/4/2022 | CARLOS MONTES |
| Plan Check Approved | 3/30/2022 | CARLOS MONTES |
| Issued | 4/1/2022 | APPLICANT |
| CofO in Progress | 8/26/2022 | ARAM AVEDISIAN |
| Permit Finaled | 10/5/2022 | MICHAEL SMITH |
| CofO Issued | 10/5/2022 | MICHAEL SMITH |
| Permit Finaled | 10/5/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/20/2021 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2021 | AMIR KASHFI |
| Sewer availability | Cleared | 1/3/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/4/2022 | DWAYNE LAURENT |
| Low Impact Development | Cleared | 3/17/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 3/23/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Ornelas F Construction Clean Up Inc; Lic. No.: 784289-B | , |
| Contractor | Ornelas F Construction; Lic. No.: 784289-B | , |
| Engineer | Basma,, Ali J; Lic. No.: NA53080 | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/6/2022 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 4/6/2022 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 4/12/2022 | Approved | JOHN HAYES |
| Sewer | 4/12/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2022 | Corrections Issued | MICHAEL TEMPLE |
| PLUMBING-Rough | 5/24/2022 | Corrections Issued | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 6/6/2022 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 6/6/2022 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 6/6/2022 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 6/6/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 6/9/2022 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 6/9/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 6/9/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 6/9/2022 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 6/9/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 6/14/2022 | Conditional Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 6/14/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 6/14/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 6/14/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/14/2022 | Partial Approval | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 6/14/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 6/21/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/21/2022 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 6/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 8/16/2022 | Approved | ARAM AVEDISIAN |
| Final | 8/16/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 8/16/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 8/16/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 8/16/2022 | Approved | ARAM AVEDISIAN |
| Final | 8/22/2022 | Corrections Issued | ARAM AVEDISIAN |
| Final | 8/26/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 8/26/2022 | Approved | ARAM AVEDISIAN |