7335 N FARMDALE AVE 91605

Certificate Information: 7335 N FARMDALE AVE 91605

Application / Permit
21010-20000-05891
Plan Check / Job No.
B21VN15624
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 23' X 42' (966 SQ. FT.) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER WFPP.
Permit Issued
Issued on 6/6/2022
Issuing Office
Current Status
CofO Issued on 6/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 OMAR GARNICA
Corrections Issued 11/25/2021 OMAR GARNICA
Plan Check Approved 6/6/2022 OMAR GARNICA
Issued 6/6/2022 APPLICANT
Building Plans Picked Up 6/8/2022 APPLICANT
CofO in Progress 4/14/2026 ROBERTO PALACIOS-LOPEZ
CofO Issued 6/17/2026 RUBEN SALAS
Permit Finaled 6/17/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/17/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 12/21/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 1/8/2022 STEVEN JIN
Construction near power lines Cleared 3/13/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 4/18/2022 ROSE MARIE SMITH
Low Impact Development Cleared 5/18/2022 JORGE MEJIA LEMUS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/6/2022 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 7/18/2022 Not Ready for Inspection MISAEL ESPARZA
Gas Test 7/18/2022 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 7/18/2022 Partial Approval MISAEL ESPARZA
Sewer 7/18/2022 Approved MISAEL ESPARZA
Footing/Foundation/Slab 7/25/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 7/25/2022 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 7/25/2022 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 7/28/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 8/23/2022 No Access for Inspection JOHN HAYES
Green Building Rough 8/23/2022 No Access for Inspection JOHN HAYES
Verify Sprinkler Sign Off 8/23/2022 No Access for Inspection JOHN HAYES
ELECTRICAL-Rough 8/29/2022 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 8/29/2022 Partial Approval JOHN HAYES
Rough-Elec/Plmb/HVAC 8/29/2022 Approved JOHN HAYES
Wood Frame 8/29/2022 Partial Approval JOHN HAYES
Interior/Exterior Lathing 9/6/2022 Approved CALEB MEISTER
PLUMBING-Rough 9/6/2022 Approved CALEB MEISTER
BUILDING-Rough-Frame 9/12/2022 Approved DAVID ANDERSON
ELECTRICAL-Rough 9/12/2022 Approved DAVID ANDERSON
Green Building Rough 9/12/2022 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 9/12/2022 Approved DAVID ANDERSON
Insulation 9/16/2022 Approved JOHN HAYES
Drywall Nailing 9/27/2022 Approved JOHN HAYES
Interior/Exterior Lathing 10/3/2022 Approved CALEB MEISTER
Final 5/13/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 5/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 5/13/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 5/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 5/13/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 6/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 6/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 6/10/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 6/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 6/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 6/16/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 6/16/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 6/16/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 6/16/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 4/10/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Green Building Final 4/10/2026 Approved ROBERTO PALACIOS-LOPEZ
Pre-Inspection 4/10/2026 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/10/2026 Approved ROBERTO PALACIOS-LOPEZ