628 1/2-3/4 W 54TH ST 90037

Certificate Information: 628 1/2-3/4 W 54TH ST 90037

Application / Permit
21010-20000-05858
Plan Check / Job No.
B21VN15478
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY TWO ACCESSORY DWELLING UNITS PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 3/25/2024
Issuing Office
Current Status
CofO Issued on 8/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2021 APPLICANT
Assigned to Plan Check Engineer 11/30/2021 DANIEL YIP
Corrections Issued 12/1/2021 DANIEL YIP
Quality Review Completed 12/6/2021 HERNAN ARREOLA
Applicant returned to address corrections 2/3/2022 DANIEL YIP
Plan Check Approved 7/26/2022 DANIEL YIP
Issued 3/25/2024 APPLICANT
CofO in Progress 8/22/2025 BARRY HACHE
Permit Finaled 8/23/2025 DEROLD HAUFF
CofO Issued 8/23/2025 DEROLD HAUFF
Permit Finaled 8/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/26/2022 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 2/8/2022 KHOUNG LE
Sewer availability Cleared 2/8/2022 KHOUNG LE
Tenant Habitability Plan Cleared 3/2/2022 PHILLIP MUNGUIA
Low Impact Development Cleared 7/6/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/12/2022 KHOUNG LE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/21/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 8/23/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 8/29/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 9/3/2024 Partial Approval CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 9/16/2024 Not Ready for Inspection CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 9/18/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 10/18/2024 Not Ready for Inspection MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/18/2024 Partial Approval MICHAEL LEWIS
Green Building Rough 10/18/2024 Not Ready for Inspection MICHAEL LEWIS
Verify Sprinkler Sign Off 10/18/2024 Not Ready for Inspection MICHAEL LEWIS
BUILDING-Rough-Frame 11/6/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 11/6/2024 Approved SABAS ALONSO
Green Building Rough 11/6/2024 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 11/6/2024 Corrections Issued SABAS ALONSO
PLUMBING-Rough 11/6/2024 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 11/6/2024 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 11/8/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 11/8/2024 Corrections Issued CRAIG DAVIS
Interior/Exterior Lathing 11/13/2024 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 11/13/2024 Not Ready for Inspection CRAIG DAVIS
Interior/Exterior Lathing 11/15/2024 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 11/15/2024 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 11/19/2024 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 11/19/2024 Partial Approval SABAS ALONSO
PLUMBING-Rough 11/19/2024 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 11/25/2024 Corrections Issued CRAIG DAVIS
Wood Frame 11/25/2024 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 12/4/2024 Not Ready for Inspection JOSE MACIAS
Green Building Rough 12/4/2024 Approved JOSE MACIAS
HVAC-Rough 12/4/2024 Corrections Issued JOSE MACIAS
PLUMBING-Rough 12/4/2024 Corrections Issued JOSE MACIAS
HVAC-Rough 12/6/2024 Approved JOHN QUINTANILLA
PLUMBING-Rough 12/6/2024 Partial Approval JOHN QUINTANILLA
BUILDING-Rough-Frame 12/10/2024 Corrections Issued CRAIG DAVIS
Insulation 12/17/2024 Approved BARRY HACHE
Drywall Nailing 12/23/2024 Corrections Issued BARRY HACHE
Drywall Nailing 12/24/2024 Approved BARRY HACHE
Gas Test 2/11/2025 Not Ready for Inspection ANTHONY RAMOS
Final 2/12/2025 Corrections Issued BARRY HACHE
Green Building Final 2/12/2025 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 2/12/2025 SGSOV Not Ready BARRY HACHE
Service/Power Release 2/12/2025 Not Ready for Inspection BARRY HACHE
Smoke Detectors 2/12/2025 Not Ready for Inspection BARRY HACHE
Final 5/15/2025 Corrections Issued BARRY HACHE
Green Building Final 5/15/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 5/15/2025 SGSOV Not Ready BARRY HACHE
Smoke Detectors 5/15/2025 Not Ready for Inspection BARRY HACHE
BUILDING-Rough-Frame 5/27/2025 Not Ready for Inspection BARRY HACHE
Final 5/27/2025 Not Ready for Inspection BARRY HACHE
Footing/Foundation/Slab 5/27/2025 Not Ready for Inspection BARRY HACHE
Green Building Final 5/27/2025 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 5/27/2025 SGSOV Not Ready BARRY HACHE
Service/Power Release 5/27/2025 Not Ready for Inspection BARRY HACHE
Smoke Detectors 5/27/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 7/25/2025 Approved BARRY HACHE
ELECTRICAL-Final 7/25/2025 Corrections Issued BARRY HACHE
Final 7/25/2025 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 7/25/2025 Approved BARRY HACHE
Green Building Final 7/25/2025 Approved BARRY HACHE
HVAC-Final 7/25/2025 Approved BARRY HACHE
PLUMBING-Final 7/25/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 7/25/2025 SGSOV Not Ready BARRY HACHE
Service/Power Release 7/25/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 7/29/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Final 7/29/2025 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Final 7/29/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Final 8/4/2025 Corrections Issued BARRY HACHE
Final 8/4/2025 Not Ready for Inspection BARRY HACHE
HVAC-Final 8/4/2025 Approved BARRY HACHE
PLUMBING-Final 8/4/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 8/4/2025 SGSOV Not Ready BARRY HACHE
Service/Power Release 8/4/2025 Not Ready for Inspection BARRY HACHE
Smoke Detectors 8/4/2025 Approved BARRY HACHE
ELECTRICAL-Final 8/6/2025 Corrections Issued BARRY HACHE
HVAC-Final 8/6/2025 Approved BARRY HACHE
PLUMBING-Final 8/6/2025 Not Ready for Inspection BARRY HACHE
Final 8/8/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Final 8/8/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 8/9/2025 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 8/9/2025 Off-Hour Fees Due
PLUMBING-Final 8/9/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Final 8/9/2025 Off-Hour Fees Due
PLUMBING-Final 8/11/2025 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Final 8/12/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Final 8/12/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 8/13/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 8/13/2025 Corrections Issued RAUL BARAJAS
Final 8/13/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Final 8/13/2025 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 8/13/2025 SGSOV Approved BARRY HACHE
Service/Power Release 8/13/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 8/20/2025 Approved BARRY HACHE
Final 8/20/2025 Corrections Issued BARRY HACHE
Service/Power Release 8/20/2025 Not Ready for Inspection BARRY HACHE
Final 8/21/2025 OK to Issue CofO BARRY HACHE
Service/Power Release 8/21/2025 Approved BARRY HACHE