628 1/2-3/4 W 54TH ST 90037
Certificate Information: 628 1/2-3/4 W 54TH ST 90037
- Application / Permit
- 21010-20000-05858
- Plan Check / Job No.
- B21VN15478
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 1-STORY TWO ACCESSORY DWELLING UNITS PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 3/25/2024
- Issuing Office
- Current Status
- CofO Issued on 8/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2021 | DANIEL YIP |
| Corrections Issued | 12/1/2021 | DANIEL YIP |
| Quality Review Completed | 12/6/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 2/3/2022 | DANIEL YIP |
| Plan Check Approved | 7/26/2022 | DANIEL YIP |
| Issued | 3/25/2024 | APPLICANT |
| CofO in Progress | 8/22/2025 | BARRY HACHE |
| Permit Finaled | 8/23/2025 | DEROLD HAUFF |
| CofO Issued | 8/23/2025 | DEROLD HAUFF |
| Permit Finaled | 8/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/26/2022 | KHOUNG LE |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2022 | KHOUNG LE |
| Sewer availability | Cleared | 2/8/2022 | KHOUNG LE |
| Tenant Habitability Plan | Cleared | 3/2/2022 | PHILLIP MUNGUIA |
| Low Impact Development | Cleared | 7/6/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/12/2022 | KHOUNG LE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/21/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 8/23/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 8/29/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 9/3/2024 | Partial Approval | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 9/16/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 9/18/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 10/18/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2024 | Partial Approval | MICHAEL LEWIS |
| Green Building Rough | 10/18/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 10/18/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 11/6/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 11/6/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 11/6/2024 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 11/6/2024 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 11/6/2024 | Not Ready for Inspection | SABAS ALONSO |
| Verify Sprinkler Sign Off | 11/6/2024 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 11/8/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 11/8/2024 | Corrections Issued | CRAIG DAVIS |
| Interior/Exterior Lathing | 11/13/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 11/13/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Interior/Exterior Lathing | 11/15/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 11/15/2024 | Not Ready for Inspection | CRAIG DAVIS |
| HVAC-Rough | 11/19/2024 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 11/19/2024 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 11/19/2024 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 11/25/2024 | Corrections Issued | CRAIG DAVIS |
| Wood Frame | 11/25/2024 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 12/4/2024 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Rough | 12/4/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 12/4/2024 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Rough | 12/4/2024 | Corrections Issued | JOSE MACIAS |
| HVAC-Rough | 12/6/2024 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 12/6/2024 | Partial Approval | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 12/10/2024 | Corrections Issued | CRAIG DAVIS |
| Insulation | 12/17/2024 | Approved | BARRY HACHE |
| Drywall Nailing | 12/23/2024 | Corrections Issued | BARRY HACHE |
| Drywall Nailing | 12/24/2024 | Approved | BARRY HACHE |
| Gas Test | 2/11/2025 | Not Ready for Inspection | ANTHONY RAMOS |
| Final | 2/12/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 2/12/2025 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 2/12/2025 | SGSOV Not Ready | BARRY HACHE |
| Service/Power Release | 2/12/2025 | Not Ready for Inspection | BARRY HACHE |
| Smoke Detectors | 2/12/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 5/15/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 5/15/2025 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 5/15/2025 | SGSOV Not Ready | BARRY HACHE |
| Smoke Detectors | 5/15/2025 | Not Ready for Inspection | BARRY HACHE |
| BUILDING-Rough-Frame | 5/27/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 5/27/2025 | Not Ready for Inspection | BARRY HACHE |
| Footing/Foundation/Slab | 5/27/2025 | Not Ready for Inspection | BARRY HACHE |
| Green Building Final | 5/27/2025 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 5/27/2025 | SGSOV Not Ready | BARRY HACHE |
| Service/Power Release | 5/27/2025 | Not Ready for Inspection | BARRY HACHE |
| Smoke Detectors | 5/27/2025 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 7/25/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 7/25/2025 | Corrections Issued | BARRY HACHE |
| Final | 7/25/2025 | Corrections Issued | BARRY HACHE |
| Footing/Foundation/Slab | 7/25/2025 | Approved | BARRY HACHE |
| Green Building Final | 7/25/2025 | Approved | BARRY HACHE |
| HVAC-Final | 7/25/2025 | Approved | BARRY HACHE |
| PLUMBING-Final | 7/25/2025 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 7/25/2025 | SGSOV Not Ready | BARRY HACHE |
| Service/Power Release | 7/25/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 7/29/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Final | 7/29/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Final | 7/29/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Final | 8/4/2025 | Corrections Issued | BARRY HACHE |
| Final | 8/4/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 8/4/2025 | Approved | BARRY HACHE |
| PLUMBING-Final | 8/4/2025 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 8/4/2025 | SGSOV Not Ready | BARRY HACHE |
| Service/Power Release | 8/4/2025 | Not Ready for Inspection | BARRY HACHE |
| Smoke Detectors | 8/4/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 8/6/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 8/6/2025 | Approved | BARRY HACHE |
| PLUMBING-Final | 8/6/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 8/8/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Final | 8/8/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 8/9/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 8/9/2025 | Off-Hour Fees Due | |
| PLUMBING-Final | 8/9/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 8/9/2025 | Off-Hour Fees Due | |
| PLUMBING-Final | 8/11/2025 | Not Ready for Inspection | WAYNE REGESTER |
| ELECTRICAL-Final | 8/12/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Final | 8/12/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 8/13/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 8/13/2025 | Corrections Issued | RAUL BARAJAS |
| Final | 8/13/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Final | 8/13/2025 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 8/13/2025 | SGSOV Approved | BARRY HACHE |
| Service/Power Release | 8/13/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 8/20/2025 | Approved | BARRY HACHE |
| Final | 8/20/2025 | Corrections Issued | BARRY HACHE |
| Service/Power Release | 8/20/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 8/21/2025 | OK to Issue CofO | BARRY HACHE |
| Service/Power Release | 8/21/2025 | Approved | BARRY HACHE |