15111 W MAYALL ST 91345

Certificate Information: 15111 W MAYALL ST 91345

Application / Permit
21010-20000-05851
Plan Check / Job No.
B21VN15462
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d)
Permit Issued
Issued on 9/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 NILOOFAR MEHRAIN
Corrections Issued 12/21/2021 NILOOFAR MEHRAIN
Quality Review Completed 12/23/2021 STEVEN KIM
Building Plans Picked Up 12/23/2021 APPLICANT
Plan Check Approved 9/27/2022 NILOOFAR MEHRAIN
Issued 9/27/2022 APPLICANT
CofO in Progress 12/14/2023 JENNIFER RABUCHIN
No Progress 2/1/2024 ROBERT GOLD
CofO in Progress 2/1/2024 ROBERT GOLD
No Progress 3/13/2024 ROBERT GOLD
CofO in Progress 3/13/2024 ROBERT GOLD
CofO in Progress 3/15/2024 JENNIFER RABUCHIN
Permit Finaled 3/22/2024 RUBEN SALAS
CofO Issued 3/22/2024 RUBEN SALAS
Permit Finaled 3/22/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/5/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/6/2022 CARLOS AGUILERA
Sewer availability Cleared 1/6/2022 CARLOS AGUILERA
Construction near power lines Cleared 3/25/2022 RIDWAN HARDY
Construction within easement Cleared 3/25/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 5/16/2022 RUEL COLE
Low Impact Development Cleared 9/15/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/19/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/20/2023 Corrections Issued JOHN COLEMAN
PLUMBING-Rough 2/23/2023 Partial Approval JENNIFER RABUCHIN
Sewer 2/23/2023 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 4/11/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 4/14/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/26/2023 Partial Approval JENNIFER RABUCHIN
Deputy Wood Construction 5/3/2023 Conditional Approval ROBERT GOLD
Deputy Drilled-In Anchors 5/5/2023 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 5/8/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/8/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 5/25/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 5/25/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 5/25/2023 Corrections Issued JENNIFER RABUCHIN
Wood Frame 5/25/2023 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/5/2023 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 6/5/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 6/5/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/5/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/5/2023 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 6/5/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 6/9/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 6/9/2023 Approved JENNIFER RABUCHIN
Insulation 6/9/2023 Approved JENNIFER RABUCHIN
Shower Pan 6/9/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 6/14/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/14/2023 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 6/26/2023 Approved JENNIFER RABUCHIN
Shower Pan 6/26/2023 Approved JENNIFER RABUCHIN
Gas Test 9/7/2023 Approved JENNIFER RABUCHIN
Service/Power Release 9/7/2023 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 9/7/2023 Approved JENNIFER RABUCHIN
Service/Power Release 10/30/2023 Approved KEVIN BERBERYAN
ELECTRICAL-Final 11/22/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/4/2023 Partial Inspection MICHEL ABAJAN
Final 12/4/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 12/4/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/4/2023 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 12/4/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 12/13/2023 Approved JENNIFER RABUCHIN
Final 12/13/2023 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 12/13/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 12/13/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/13/2023 SGSOV Approved JENNIFER RABUCHIN
Final 2/12/2024 Corrections Issued JENNIFER RABUCHIN