15111 W MAYALL ST 91345
Certificate Information: 15111 W MAYALL ST 91345
- Application / Permit
- 21010-20000-05851
- Plan Check / Job No.
- B21VN15462
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d)
- Permit Issued
- Issued on 9/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 12/21/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 12/23/2021 | STEVEN KIM |
| Building Plans Picked Up | 12/23/2021 | APPLICANT |
| Plan Check Approved | 9/27/2022 | NILOOFAR MEHRAIN |
| Issued | 9/27/2022 | APPLICANT |
| CofO in Progress | 12/14/2023 | JENNIFER RABUCHIN |
| No Progress | 2/1/2024 | ROBERT GOLD |
| CofO in Progress | 2/1/2024 | ROBERT GOLD |
| No Progress | 3/13/2024 | ROBERT GOLD |
| CofO in Progress | 3/13/2024 | ROBERT GOLD |
| CofO in Progress | 3/15/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 3/22/2024 | RUBEN SALAS |
| CofO Issued | 3/22/2024 | RUBEN SALAS |
| Permit Finaled | 3/22/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/5/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/6/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 3/25/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/25/2022 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 5/16/2022 | RUEL COLE |
| Low Impact Development | Cleared | 9/15/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 9/19/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/20/2023 | Corrections Issued | JOHN COLEMAN |
| PLUMBING-Rough | 2/23/2023 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 2/23/2023 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/11/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/14/2023 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2023 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Wood Construction | 5/3/2023 | Conditional Approval | ROBERT GOLD |
| Deputy Drilled-In Anchors | 5/5/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 5/8/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/25/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 5/25/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/25/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 5/25/2023 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/5/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/5/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 6/5/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/5/2023 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/5/2023 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 6/5/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/9/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 6/9/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 6/9/2023 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 6/9/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 6/14/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/14/2023 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/26/2023 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 6/26/2023 | Approved | JENNIFER RABUCHIN |
| Gas Test | 9/7/2023 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 9/7/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 9/7/2023 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 10/30/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 11/22/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/4/2023 | Partial Inspection | MICHEL ABAJAN |
| Final | 12/4/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 12/4/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/4/2023 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 12/4/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/13/2023 | Approved | JENNIFER RABUCHIN |
| Final | 12/13/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 12/13/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/13/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Final | 2/12/2024 | Corrections Issued | JENNIFER RABUCHIN |