5438 N LEGHORN AVE 91401
Certificate Information: 5438 N LEGHORN AVE 91401
- Application / Permit
- 21010-20000-05849
- Plan Check / Job No.
- B21VN15460
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 35'-1" X 47'-0" 2-STORY SFD W/ 7'-10" X 23'-6" TRELLIS PATIO AT REAR. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/26/2022
- Issuing Office
- Current Status
- CofO Issued on 12/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | RAPHAEL ROSAS |
| Corrections Issued | 11/22/2021 | RAPHAEL ROSAS |
| Quality Review Completed | 11/24/2021 | STEVEN KIM |
| Applicant returned to address corrections | 1/11/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 1/21/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 1/24/2022 | APPLICANT |
| Issued | 1/26/2022 | APPLICANT |
| CofO in Progress | 10/6/2022 | RAFAEL CORTES |
| Permit Finaled | 12/9/2022 | MICHAEL SMITH |
| CofO Issued | 12/9/2022 | MICHAEL SMITH |
| Permit Finaled | 12/9/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/22/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/22/2021 | CARLOS AGUILERA |
| ZA Case | Cleared | 12/6/2021 | MIGUEL GAMBOA |
| Low Impact Development | Cleared | 12/13/2021 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 12/14/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 12/31/2021 | ROBERT DUFF |
| Frnt yard landscape/Water mgmt | Cleared | 1/10/2022 | MIGUEL GAMBOA |
| Hold | Cleared | 2/3/2022 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/7/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 2/10/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Underground Mechanical | 2/14/2022 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 2/17/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 2/22/2022 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 3/10/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 3/10/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 3/10/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Wood Frame | 3/30/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 3/31/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 4/5/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 4/12/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 4/12/2022 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 4/12/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 4/12/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 4/12/2022 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 4/12/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 4/20/2022 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 4/20/2022 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 4/29/2022 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 4/29/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Drywall Nailing | 5/5/2022 | Conditional Approval | MICHAEL TEMPLE |
| Shower Pan | 5/9/2022 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 5/25/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 5/25/2022 | Approved | CHRISTOPHE COCHRAN |
| Gas Test | 6/27/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Final | 6/28/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Gas Test | 6/28/2022 | Corrections Issued | RAFAEL CORTES |
| HVAC-Final | 6/28/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Final | 6/28/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Final | 7/1/2022 | Not Ready for Inspection | RAFAEL CORTES |
| HVAC-Final | 7/1/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Final | 7/1/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Final | 7/8/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Gas Test | 7/8/2022 | Approved | RAFAEL CORTES |
| ELECTRICAL-Final | 7/18/2022 | Corrections Issued | RAFAEL CORTES |
| PLUMBING-Final | 7/18/2022 | Corrections Issued | RAFAEL CORTES |
| ELECTRICAL-Final | 7/28/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 7/28/2022 | Corrections Issued | RAFAEL CORTES |
| Footing/Foundation/Slab | 7/28/2022 | Approved | RAFAEL CORTES |
| Green Building Final | 7/28/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Final | 7/28/2022 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 7/28/2022 | SGSOV Not Ready | RAFAEL CORTES |
| Service/Power Release | 7/28/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Smoke Detectors | 7/28/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 9/29/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 9/29/2022 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 9/29/2022 | SGSOV Approved | RAFAEL CORTES |
| Service/Power Release | 9/29/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Smoke Detectors | 9/29/2022 | Corrections Issued | RAFAEL CORTES |
| Final | 10/5/2022 | OK to Issue CofO | RAFAEL CORTES |
| Service/Power Release | 10/5/2022 | Approved | RAFAEL CORTES |
| Smoke Detectors | 10/5/2022 | Approved | RAFAEL CORTES |