12031 W ADDISON ST 91607
Certificate Information: 12031 W ADDISON ST 91607
- Application / Permit
- 21010-20000-05814
- Plan Check / Job No.
- B21VN15340
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRR. SHAPED 34'-6" x 65'-3.25" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
- Permit Issued
- Issued on 5/23/2022
- Issuing Office
- Current Status
- CofO Issued on 8/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | SEAN SHAHMIRI |
| Corrections Issued | 11/22/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 11/22/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 11/23/2021 | APPLICANT |
| Applicant returned to address corrections | 4/19/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 5/23/2022 | SEAN SHAHMIRI |
| Issued | 5/23/2022 | APPLICANT |
| CofO in Progress | 7/10/2023 | JACK KARGODORIAN |
| Permit Finaled | 8/9/2023 | RUBEN SALAS |
| CofO Issued | 8/9/2023 | RUBEN SALAS |
| Permit Finaled | 8/9/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Specific Plan | Cleared | 11/29/2021 | ERIN NASH |
| Address approval | Cleared | 1/21/2022 | JOSE DUARTE-DIAZ |
| Permit | Cleared | 1/21/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 1/22/2022 | JOSE DUARTE-DIAZ |
| Trees in Parkway | Cleared | 2/3/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 2/15/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 2/16/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 3/28/2022 | DWAYNE LAURENT |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/8/2022 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 7/8/2022 | Partial Approval | MATT KELLERMAN |
| Underground Mechanical | 7/8/2022 | Approved | MATT KELLERMAN |
| Footing/Foundation/Slab | 7/15/2022 | Approved | THOMAS FINNILA |
| Underground Mechanical | 7/15/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 11/30/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 12/2/2022 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 12/16/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2023 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/13/2023 | Approved | JACK KARGODORIAN |
| Green Building Rough | 1/13/2023 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 1/13/2023 | Approved | JACK KARGODORIAN |
| Insulation | 2/1/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/1/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/6/2023 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 2/6/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 2/9/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/16/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 6/21/2023 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Final | 6/21/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 6/21/2023 | Approved | JACK KARGODORIAN |
| Service/Power Release | 6/21/2023 | Approved | JACK KARGODORIAN |
| Final | 7/7/2023 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 7/7/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 7/7/2023 | Approved | JACK KARGODORIAN |