- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- CofO Issued on 11/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | CARLOS MONTES |
| Corrections Issued | 11/27/2021 | CARLOS MONTES |
| Quality Review Completed | 11/29/2021 | HERNAN ARREOLA |
| Plan Check Approved | 4/20/2022 | CARLOS MONTES |
| Issued | 4/26/2022 | APPLICANT |
| CofO in Progress | 11/7/2022 | ARAM AVEDISIAN |
| CofO Issued | 11/12/2022 | MICHAEL SMITH |
| Permit Finaled | 11/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2021 | DAGOVERTO GUERRERO |
| Miscellaneous | Cleared | 12/9/2021 | DANIEL SCHNEIDEREIT |
| Sewer availability | Cleared | 12/9/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 3/24/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 4/7/2022 | ABDULLAH SADOZAI |
Contact Information
| Architect | Kadribegovic,, Nerin; Lic. No.: C32104 | 2260 EVERLEE LN LOS ANGELES, CA 90041 |
| Architect | Kadribegovic,, Nerin; Lic. No.: NA32104 | , |
| Contractor | Owner-Builder | , |
| Engineer | Garza,, Omar Leonel; Lic. No.: NA5593 | , |
| Engineer | Garza,, Omar Leonel; Lic. No.: S5593 | 600 WILSHIRE BLVD 760 LOS ANGELES, CA 90017 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/6/2022 | Partial Approval | RAUL OLAGI |
| Sewer | 5/6/2022 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 5/19/2022 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 5/19/2022 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 5/24/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/3/2022 | Partial Approval | MATT KELLERMAN |
| Pre-Inspection | 6/3/2022 | Partial Approval | MATT KELLERMAN |
| Deputy Reinf. Concrete | 6/7/2022 | Conditional Approval | JOHN HAYES |
| Footing/Foundation/Slab | 6/9/2022 | Approved | MATT KELLERMAN |
| BUILDING-Rough-Frame | 7/22/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 7/22/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 7/22/2022 | Conditional Approval | ARAM AVEDISIAN |
| HVAC-Rough | 7/22/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/22/2022 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 7/22/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/4/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 8/4/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 8/4/2022 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 8/10/2022 | Corrections Issued | ASHLEY THOMPSON |
| Drywall Nailing | 8/17/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 9/1/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Final | 9/9/2022 | Approved | ARAM AVEDISIAN |
| Gas Test | 9/9/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 9/9/2022 | Approved | ARAM AVEDISIAN |
| Final | 10/13/2022 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 10/13/2022 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 10/13/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Final | 10/27/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 10/27/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 10/27/2022 | Approved | ARAM AVEDISIAN |
| Final | 11/7/2022 | OK to Issue CofO | ARAM AVEDISIAN |