20512 W BIRMINGHAM WAY 91326
Certificate Information: 20512 W BIRMINGHAM WAY 91326
- Application / Permit
- 21010-20000-05792
- Plan Check / Job No.
- B21VN15276
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 12'-0" X 18'-0" TRELLIS TO THE REAR OF THE EXISTING SINGLE FAMILY DWELLING PER ENGINEERING
- Permit Issued
- Issued on 3/13/2022
- Issuing Office
- Current Status
- CofO in Progress on 1/13/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | COLIN LOREDO |
| Corrections Issued | 12/14/2021 | COLIN LOREDO |
| Quality Review Completed | 12/21/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 12/22/2021 | APPLICANT |
| Plan Check Approved | 2/14/2022 | COLIN LOREDO |
| Issued | 3/13/2022 | APPLICANT |
| CofO in Progress | 1/31/2024 | JEFFREY PARD |
| No Progress | 1/13/2025 | HENRY KIM |
| CofO in Progress | 1/13/2025 | HENRY KIM |
Permit Application Clearance Information
| Miscellaneous | Cleared | 1/18/2022 | RYAN LY |
| Miscellaneous | Cleared | 1/18/2022 | RYAN LY |
| Miscellaneous | Cleared | 1/18/2022 | RYAN LY |
| Miscellaneous | Cleared | 1/18/2022 | RYAN LY |
| Miscellaneous | Cleared | 1/18/2022 | RYAN LY |
| ZA Case | Cleared | 1/18/2022 | RYAN LY |
| "T" removal | Cleared | 1/19/2022 | RYAN LY |
| ZA Case | Cleared | 1/19/2022 | RYAN LY |
| ZI | Cleared | 1/25/2022 | DANG NGUYEN |
| Grading Pre-Inspection | Cleared | 2/14/2022 | COLIN LOREDO |
Contact Information
| Contractor | Pedro Gonzalez Pools & Construction; Lic. No.: 1058560-B | 13948 DEL SUR STREET PACOIMA, CA 91331 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/26/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 1/29/2024 | Approved | JEFFREY PARD |
| Drywall Nailing | 1/29/2024 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 1/29/2024 | Approved | JEFFREY PARD |
| Final | 1/29/2024 | OK to Issue CofO | JEFFREY PARD |
| Green Building Final | 1/29/2024 | Approved | JEFFREY PARD |
| Green Building Rough | 1/29/2024 | Approved | JEFFREY PARD |
| Reinforced Masonry Frame | 1/29/2024 | Approved | JEFFREY PARD |
| Smoke Detectors | 1/29/2024 | Approved | JEFFREY PARD |
| Structural Steel Frame | 1/29/2024 | Approved | JEFFREY PARD |
| Special/Order Compliance | 1/14/2025 | Corrections Issued | JEFFREY PARD |