14637 W POLK ST 91342

Certificate Information: 14637 W POLK ST 91342

Application / Permit
21010-20000-05779
Plan Check / Job No.
B21VN15224
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY ADU AT REAR OF LOT.
Permit Issued
Issued on 4/26/2022
Issuing Office
Current Status
CofO Issued on 11/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 JOE VO
Corrections Issued 11/28/2021 JOE VO
Quality Review Completed 12/2/2021 HERNAN ARREOLA
Plan Check Approved 4/20/2022 JOE VO
Issued 4/26/2022 APPLICANT
CofO in Progress 11/7/2022 ARAM AVEDISIAN
Permit Finaled 11/12/2022 MICHAEL SMITH
CofO Issued 11/12/2022 MICHAEL SMITH
Permit Finaled 11/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/8/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 12/9/2021 DAGOVERTO GUERRERO
Miscellaneous Cleared 12/9/2021 DANIEL SCHNEIDEREIT
Sewer availability Cleared 12/17/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 3/11/2022 RIDWAN HARDY
Low Impact Development Cleared 3/25/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 4/7/2022 CARLOS AGUILERA

Contact Information

Architect Kadribegovic,, Nerin; Lic. No.: NA32104       ,
Contractor Owner-Builder       ,
Engineer Garza,, Omar Leonel; Lic. No.: NA5593       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/6/2022 Partial Approval RAUL OLAGI
Sewer 5/6/2022 Approved RAUL OLAGI
Footing/Foundation/Slab 5/19/2022 Corrections Issued JOHN HAYES
PLUMBING-Rough 5/19/2022 Not Ready for Inspection JOHN HAYES
Underground Mechanical 5/24/2022 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 6/3/2022 Partial Approval MATT KELLERMAN
Pre-Inspection 6/3/2022 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 6/9/2022 Approved MATT KELLERMAN
BUILDING-Rough-Frame 7/22/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 7/22/2022 Approved ARAM AVEDISIAN
Green Building Rough 7/22/2022 Conditional Approval ARAM AVEDISIAN
HVAC-Rough 7/22/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 7/22/2022 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 7/22/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 8/4/2022 Approved ARAM AVEDISIAN
Green Building Rough 8/4/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 8/4/2022 Partial Approval ARAM AVEDISIAN
Insulation 8/10/2022 Corrections Issued ASHLEY THOMPSON
Drywall Nailing 8/17/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 9/1/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 9/9/2022 Approved ARAM AVEDISIAN
Gas Test 9/9/2022 Approved ARAM AVEDISIAN
PLUMBING-Final 9/9/2022 Approved ARAM AVEDISIAN
Final 10/13/2022 Corrections Issued THOMAS FINNILA
HVAC-Final 10/13/2022 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 10/13/2022 SGSOV Not Ready THOMAS FINNILA
Final 10/27/2022 Corrections Issued ARAM AVEDISIAN
Green Building Final 10/27/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 10/27/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 10/27/2022 Approved ARAM AVEDISIAN
Final 11/7/2022 OK to Issue CofO ARAM AVEDISIAN