6713 N JAMIESON AVE 91335
Certificate Information: 6713 N JAMIESON AVE 91335
- Application / Permit
- 21010-20000-05768
- Plan Check / Job No.
- B21VN15172
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW DETACHED 49'X21'6"ACCESSORY DWELLING UNIT PER LAMC 12.22A.33 (c) & (d).
- Permit Issued
- Issued on 6/22/2023
- Issuing Office
- Current Status
- CofO Issued on 12/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 11/14/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 3/30/2022 | HAYATO TSUCHIYA |
| Plan Check Approved | 4/11/2022 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 4/11/2022 | APPLICANT |
| Issued | 6/22/2023 | APPLICANT |
| CofO in Progress | 12/8/2023 | JEFFREY BULL |
| Permit Finaled | 12/21/2023 | JOHN JANSON |
| CofO Issued | 12/21/2023 | JOHN JANSON |
| Permit Finaled | 12/21/2023 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 11/17/2021 | DANG NGUYEN |
| Address approval | Cleared | 11/18/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 11/19/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 1/6/2022 | ANTHONY VARGAS |
| Hydrant and Access approval | Cleared | 2/3/2022 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 3/9/2022 | TINA MIRANDA |
| Construction within easement | Cleared | 3/9/2022 | TINA MIRANDA |
| Roof/Waste drainage to street | Cleared | 3/9/2022 | DAGOVERTO GUERRERO |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/17/2023 | Partial Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 7/21/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Partial Approval | VINCENT HANLEY |
| Wood Frame | 8/4/2023 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 8/14/2023 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 8/14/2023 | Approved | JEFFREY BULL |
| Sewer | 8/14/2023 | Approved | JEFFREY BULL |
| Underground Mechanical | 8/14/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 8/21/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 8/21/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 8/21/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 8/21/2023 | Partial Approval | JEFFREY BULL |
| Verify Sprinkler Sign Off | 8/21/2023 | Approved | JEFFREY BULL |
| Insulation | 8/28/2023 | Corrections Issued | JEFFREY BULL |
| Interior/Exterior Lathing | 8/28/2023 | Not Ready for Inspection | JEFFREY BULL |
| Shower Pan | 8/28/2023 | Not Ready for Inspection | JEFFREY BULL |
| Insulation | 9/5/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 9/5/2023 | Approved | JEFFREY BULL |
| Shower Pan | 9/5/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 9/8/2023 | Not Ready for Inspection | JEFFREY BULL |
| Drywall Nailing | 9/14/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 12/6/2023 | Approved | JEFFREY BULL |
| Final | 12/6/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 12/6/2023 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Final | 12/6/2023 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Final | 12/6/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 12/6/2023 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 12/6/2023 | Not Required | JEFFREY BULL |
| Smoke Detectors | 12/6/2023 | Approved | JEFFREY BULL |
| Final | 12/8/2023 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 12/8/2023 | Approved | JEFFREY BULL |
| HVAC-Final | 12/8/2023 | Approved | JEFFREY BULL |