20617 W QUEDO DR 91364

Certificate Information: 20617 W QUEDO DR 91364

Application / Permit
21010-20000-05757
Plan Check / Job No.
B21VN15132
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRREGULAR SHAPED 83'-0" X 59'-0", 2-STORY SINGLE FAMLIY DWELLING WITH ATTACHED 2-CAR GARAGE AND ATTACHED TRELLIS. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/15/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 COLIN LOREDO
Corrections Issued 11/30/2021 COLIN LOREDO
Quality Review Completed 11/30/2021 OMID HEDAYAT
Building Plans Picked Up 11/30/2021 APPLICANT
Plan Check Approved 8/12/2022 DAWN MC NULTY
Issued 9/15/2022 APPLICANT
CofO in Progress 11/14/2025 SEAN WIRCH
Permit Finaled 11/21/2025 MICHAEL PELHAM
CofO Issued 11/21/2025 MICHAEL PELHAM
Permit Finaled 11/21/2025 MICHAEL PELHAM

Permit Application Clearance Information

Low Impact Development Cleared 6/7/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 6/8/2022 LEE GUILBEAUX
Hydrant and Access approval Cleared 7/7/2022 ERIC FRENCH
Eng Process Fee Ord 176,300 Cleared 7/26/2022 LEE GUILBEAUX
Sewer availability Cleared 7/26/2022 LEE GUILBEAUX
GPI Written Notices Cleared 8/12/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 8/12/2022 COLIN LOREDO

Contact Information

Architect Janev,, Valentine S; Lic. No.: C19379 19261 WELLS DRIVE      TARZANA, CA 91356
Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/29/2023 Partial Approval PETER FOLLING
Sewer 6/29/2023 Approved PETER FOLLING
Footing/Foundation/Slab 7/18/2023 Partial Approval PETER FOLLING
Footing/Foundation/Slab 7/21/2023 No Access for Inspection JOHN KIDWELL
Footing/Foundation/Slab 7/25/2023 Approved PETER FOLLING
Deputy Reinf. Concrete 8/1/2023 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 8/18/2023 Partial Approval PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 10/17/2023 Corrections Issued PETER FOLLING
BUILDING-Rough-Frame 12/1/2023 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 12/1/2023 Approved JOHN KIDWELL
Green Building Rough 12/1/2023 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 12/1/2023 Approved JOHN KIDWELL
PLUMBING-Rough 12/1/2023 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 12/1/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 12/20/2023 Approved JOHN KIDWELL
Green Building Rough 12/20/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 12/20/2023 Partial Approval JOHN KIDWELL
Drywall Nailing 1/19/2024 Approved JOHN KIDWELL
Insulation 1/19/2024 Approved JOHN KIDWELL
Shower Pan 3/1/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 3/19/2024 Approved MORRIS JACKSON
Final 12/31/2024 Corrections Issued JOHN HAYES
Green Building Final 12/31/2024 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 12/31/2024 SGSOV Approved JOHN HAYES
Service/Power Release 12/31/2024 Not Ready for Inspection JOHN HAYES
Smoke Detectors 12/31/2024 Approved JOHN HAYES
Final 3/3/2025 Corrections Issued JOHN HAYES
Green Building Final 3/3/2025 Approved JOHN HAYES
Service/Power Release 3/3/2025 Not Ready for Inspection JOHN HAYES
Deputy Wood Construction 3/6/2025 Partial Approval SEAN WIRCH
Service/Power Release 3/19/2025 Approved SEAN WIRCH
Final 11/17/2025 OK to Issue CofO SEAN WIRCH