5189 N WOODLEY AVE 91436

Certificate Information: 5189 N WOODLEY AVE 91436

Application / Permit
21010-20000-05755
Plan Check / Job No.
B21VN15129
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY (64'-4"x57'-0"), 4240 SQFT SINGLE FAMILY DWELLING W/ATT 2-CAR GARAGE (420 SQFT) AND REAR COVERED PATIO (200 SQFT) W/ FRONT COVERED PORCH (100 SQFT) W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/7/2022
Issuing Office
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2021 APPLICANT
Assigned to Plan Check Engineer 11/11/2021 PETER MOSESIAN
Corrections Issued 11/11/2021 PETER MOSESIAN
Building Plans Picked Up 11/18/2021 APPLICANT
Quality Review Completed 11/19/2021 OMID HEDAYAT
Plan Check Approved 5/24/2022 PETER MOSESIAN
Issued 6/7/2022 APPLICANT
CofO in Progress 8/29/2023 VINCENT HANLEY
CofO Issued 9/5/2023 JOHN JANSON
Permit Finaled 9/5/2023 JOHN JANSON

Permit Application Clearance Information

Hydrant and Access approval Cleared 12/3/2021 MATTHEW CRAIG
Low Impact Development Cleared 4/13/2022 CHRIS VONG
Eng Process Fee Ord 176,300 Cleared 4/18/2022 CARLOS AGUILERA
Permit Cleared 4/18/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/18/2022 CARLOS AGUILERA
Sewer availability Cleared 4/18/2022 CARLOS AGUILERA
Trees in Parkway Cleared 5/13/2022 ADALBERTO VERA

Contact Information

Architect Janev,, Valentine S; Lic. No.: C19379 19261 WELLS DRIVE      TARZANA, CA 91356
Contractor Advance Home Improvement Inc; Lic. No.: 772769-B 17337 VENTURA BLVD STE 211      ENCINO, CA 91316
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/15/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 6/15/2022 Partial Approval VINCENT HANLEY
Underground Mechanical 6/15/2022 Partial Approval VINCENT HANLEY
Deputy Reinf. Concrete 6/17/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 6/22/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 7/14/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/14/2022 Partial Approval VINCENT HANLEY
Green Building Rough 9/14/2022 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 10/6/2022 Approved VINCENT HANLEY
HVAC-Rough 10/6/2022 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 10/13/2022 Approved VINCENT HANLEY
PLUMBING-Rough 10/13/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 10/19/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Approved VINCENT HANLEY
Green Building Rough 10/19/2022 Approved VINCENT HANLEY
MERV13>=Rough 10/19/2022 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 10/19/2022 Approved VINCENT HANLEY
Insulation 11/1/2022 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 11/1/2022 Partial Approval VINCENT HANLEY
Shower Pan 11/1/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/7/2022 Approved VINCENT HANLEY
Drywall Nailing 11/18/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 3/8/2023 Approved VINCENT HANLEY
Final 3/8/2023 Corrections Issued VINCENT HANLEY
Green Building Final 3/8/2023 Approved VINCENT HANLEY
HVAC-Final 3/8/2023 Corrections Issued VINCENT HANLEY
MERV13>=Final 3/8/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/8/2023 SGSOV Approved VINCENT HANLEY
Service/Power Release 3/8/2023 Approved VINCENT HANLEY
Smoke Detectors 3/8/2023 Approved VINCENT HANLEY
ELECTRICAL-Final 4/4/2023 Approved VINCENT HANLEY
Final 4/4/2023 Corrections Issued VINCENT HANLEY
HVAC-Final 4/4/2023 Approved VINCENT HANLEY
PLUMBING-Final 4/4/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/4/2023 SGSOV Approved VINCENT HANLEY
Final 8/29/2023 OK to Issue CofO VINCENT HANLEY