5918 N CALVIN AVE 91356
Certificate Information: 5918 N CALVIN AVE 91356
- Application / Permit
- 21010-20000-05709
- Plan Check / Job No.
- B21VN15027
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 44'5" X 19'7" ONE STORY DETACHED ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33 (C) , (D) AND (G) , NFPA-13R FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 8/9/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | RARES BODEA |
| Corrections Issued | 12/2/2021 | RARES BODEA |
| Quality Review Completed | 12/10/2021 | STEVEN KIM |
| Building Plans Picked Up | 12/10/2021 | APPLICANT |
| Applicant returned to address corrections | 5/31/2022 | RARES BODEA |
| Plan Check Approved | 8/9/2022 | RARES BODEA |
| Issued | 8/9/2022 | APPLICANT |
| CofO in Progress | 3/26/2024 | SEAN WIRCH |
| Permit Finaled | 4/23/2024 | DANIEL ORRANTE |
| CofO Issued | 4/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/4/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 3/29/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 4/28/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 5/11/2022 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/5/2023 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 5/9/2023 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 6/5/2023 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2023 | Conditional Approval | JOHN KIDWELL |
| Pre-Inspection | 6/15/2023 | Partial Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 7/11/2023 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 7/11/2023 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 7/19/2023 | Approved | SEAN WIRCH |
| Drywall Nailing | 7/19/2023 | Not Ready for Inspection | SEAN WIRCH |
| Green Building Rough | 7/19/2023 | Approved | SEAN WIRCH |
| Insulation | 7/19/2023 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 7/19/2023 | Approved | SEAN WIRCH |
| Shower Pan | 7/19/2023 | Approved | SEAN WIRCH |
| Verify Sprinkler Sign Off | 7/19/2023 | Approved | SEAN WIRCH |
| Drywall Nailing | 7/26/2023 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 11/2/2023 | Approved | SEAN WIRCH |
| Final | 11/3/2023 | Partial Inspection | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Approved | SEAN WIRCH |
| Smoke Detectors | 11/3/2023 | Approved | SEAN WIRCH |
| Final | 3/22/2024 | OK to Issue CofO | SEAN WIRCH |
| Footing/Foundation/Slab | 3/22/2024 | Approved | SEAN WIRCH |
| Green Building Final | 3/22/2024 | Approved | SEAN WIRCH |
| HVAC-Final | 3/22/2024 | Approved | SEAN WIRCH |
| PLUMBING-Final | 3/22/2024 | Approved | SEAN WIRCH |
| Service/Power Release | 3/22/2024 | Approved | SEAN WIRCH |