13560 N KISMET AVE 91342
Certificate Information: 13560 N KISMET AVE 91342
- Application / Permit
- 21010-20000-05708
- Plan Check / Job No.
- B21VN15025
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1-Story Detached ADU.
- Permit Issued
- Issued on 12/10/2021
- Issuing Office
- Current Status
- CofO Issued on 5/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2021 | JOE VO |
| Corrections Issued | 11/26/2021 | JOE VO |
| Quality Review Completed | 11/29/2021 | HERNAN ARREOLA |
| Plan Check Approved | 12/7/2021 | JOE VO |
| Issued | 12/10/2021 | APPLICANT |
| CofO in Progress | 4/21/2022 | JOHN HAYES |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
| CofO Issued | 5/14/2022 | MICHAEL SMITH |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/1/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2021 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 12/1/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/1/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Southeast Home Builders Inc; Lic. No.: 1055627-B | 15839 LASSEN STREET NORTH HILLS, CA 91343 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/15/2021 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 12/22/2021 | Partial Inspection | JOHN HAYES |
| Sewer | 12/22/2021 | Partial Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 1/21/2022 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 1/21/2022 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 1/25/2022 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 1/25/2022 | Approved | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 2/1/2022 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 2/1/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 2/15/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 2/15/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 2/15/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 2/15/2022 | Not Ready for Inspection | JOHN HAYES |
| Shower Pan | 2/15/2022 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 2/15/2022 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 2/15/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 2/23/2022 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 2/23/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2022 | Approved | JOHN HAYES |
| Gas Test | 2/23/2022 | Approved | JOHN HAYES |
| Green Building Rough | 2/23/2022 | Approved | JOHN HAYES |
| HVAC-Rough | 2/23/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 2/23/2022 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 2/23/2022 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/23/2022 | SGSOV Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 2/23/2022 | Approved | JOHN HAYES |
| Insulation | 2/28/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 2/28/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 3/2/2022 | Approved | JOHN HAYES |
| Service/Power Release | 3/17/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Final | 4/5/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 4/5/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 4/5/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 4/5/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 4/5/2022 | Not Ready for Inspection | JOHN HAYES |
| Service/Power Release | 4/5/2022 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 4/5/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 4/20/2022 | Approved | JOHN HAYES |
| Final | 4/20/2022 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 4/20/2022 | Approved | JOHN HAYES |
| HVAC-Final | 4/20/2022 | Approved | JOHN HAYES |
| PLUMBING-Final | 4/20/2022 | Approved | JOHN HAYES |
| Service/Power Release | 4/20/2022 | Approved | JOHN HAYES |
| Smoke Detectors | 4/20/2022 | Approved | JOHN HAYES |
| Verify Rec and Parks Fee Memo | 4/20/2022 | Approved | JOHN HAYES |