17552 W HART ST 91406

Certificate Information: 17552 W HART ST 91406

Application / Permit
21010-20000-05680
Plan Check / Job No.
B21VN14884
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 3/12/2022
Issuing Office
Current Status
CofO Issued on 12/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 KEVIN MORALES
Corrections Issued 11/4/2021 KEVIN MORALES
Plan Check Approved 2/28/2022 KEVIN MORALES
Issued 3/12/2022 APPLICANT
CofO in Progress 12/8/2022 SEAN HAUPT
Permit Finaled 12/20/2022 MICHAEL SMITH
CofO Issued 12/20/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/8/2021 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 11/9/2021 AMIR KASHFI
Permit Cleared 11/9/2021 AMIR KASHFI
Sewer availability Cleared 12/1/2021 AMIR KASHFI
Low Impact Development Cleared 2/8/2022 KHAING AYE
Roof/Waste drainage to street Cleared 2/14/2022 AMIR KASHFI
Construction near power lines Cleared 2/18/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/29/2022 Not Ready for Inspection DAVID SCANTLIN
Sewer 5/9/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 5/19/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 8/1/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 8/1/2022 Approved SEAN HAUPT
Green Building Rough 8/1/2022 Approved SEAN HAUPT
HVAC-Rough 8/1/2022 Approved SEAN HAUPT
PLUMBING-Rough 8/1/2022 Approved SEAN HAUPT
Verify Sprinkler Sign Off 8/1/2022 Approved SEAN HAUPT
Insulation 8/17/2022 Approved JUSTIN HAWLEY
Insulation 8/24/2022 Approved SEAN HAUPT
Drywall Nailing 9/7/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 9/7/2022 Approved SEAN HAUPT
ELECTRICAL-Final 10/18/2022 Approved SEAN HAUPT
Final 10/18/2022 Corrections Issued SEAN HAUPT
Green Building Final 10/18/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Final 10/18/2022 Approved SEAN HAUPT
PLUMBING-Final 10/18/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 10/18/2022 SGSOV Approved SEAN HAUPT
Service/Power Release 10/18/2022 Not Ready for Inspection SEAN HAUPT
Smoke Detectors 10/18/2022 Approved SEAN HAUPT
Final 12/7/2022 OK to Issue CofO SEAN HAUPT
Green Building Final 12/7/2022 Approved SEAN HAUPT
Service/Power Release 12/7/2022 Not Required SEAN HAUPT