13800 W CANTLAY ST 91405
Certificate Information: 13800 W CANTLAY ST 91405
- Application / Permit
- 21010-20000-05679
- Plan Check / Job No.
- B21VN14883
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 28'-10" X 23'-10" NEW DETACHED 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d). ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 4/23/2022
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/11/2021 | PARISA ZAHABI |
| Corrections Issued | 11/13/2021 | PARISA ZAHABI |
| Quality Review Completed | 11/15/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 11/16/2021 | APPLICANT |
| Plan Check Approved | 4/7/2022 | COLIN LOREDO |
| Issued | 4/23/2022 | APPLICANT |
| CofO in Progress | 12/22/2022 | GREGG CUMMINGS |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 2/3/2022 | JOHN CONNEALLY |
| Sewer availability | Cleared | 2/4/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 2/16/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 3/31/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 5/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 5/18/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2022 | Partial Approval | GREGG CUMMINGS |
| Pre-Inspection | 6/16/2022 | Partial Inspection | WILLIAM WREN |
| Deputy Drilled-In Anchors | 6/22/2022 | Conditional Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/11/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 7/11/2022 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 7/15/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 7/15/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/19/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 7/19/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 7/19/2022 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 7/19/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/25/2022 | Corrections Issued | GREGG CUMMINGS |
| Insulation | 7/25/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/29/2022 | Corrections Issued | GREGG CUMMINGS |
| Drywall Nailing | 7/29/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/29/2022 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 8/1/2022 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 8/17/2022 | Partial Inspection | WILLIAM WREN |
| Interior/Exterior Lathing | 8/18/2022 | Approved | DAVID MATSON |
| ELECTRICAL-Rough | 8/22/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 8/30/2022 | Partial Approval | MICHEL ABAJAN |
| Sewer | 9/9/2022 | Approved | CALEB MEISTER |
| Underground Mechanical | 9/16/2022 | Approved | WILLIAM WREN |
| Pre-Inspection | 10/28/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/3/2022 | Approved | GREGG CUMMINGS |
| Final | 11/3/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 11/3/2022 | Approved | GREGG CUMMINGS |
| Final | 12/9/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 12/9/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 12/9/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 12/16/2022 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/16/2022 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 12/16/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 12/16/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 12/21/2022 | Approved | GREGG CUMMINGS |
| Final | 12/21/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 12/21/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 12/21/2022 | Approved | GREGG CUMMINGS |
| Service/Power Release | 12/21/2022 | Approved | GREGG CUMMINGS |