862 1/4-3/4 W 47TH ST 90037

Certificate Information: 862 1/4-3/4 W 47TH ST 90037

Application / Permit
21010-20000-05663
Plan Check / Job No.
B21VN14861
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. TWO NEW DETACHED ACCESSORY DWELLING UNITS PER CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33(c)-(d), (g). “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 7/18/2022
Issuing Office
Current Status
CofO Issued on 6/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2021 APPLICANT
Assigned to Plan Check Engineer 11/15/2021 KEVIN MORALES
Corrections Issued 11/15/2021 KEVIN MORALES
Applicant returned to address corrections 1/19/2022 KEVIN MORALES
Applicant returned to address corrections 1/21/2022 KEVIN MORALES
Applicant returned to address corrections 2/8/2022 KEVIN MORALES
Applicant returned to address corrections 3/4/2022 KEVIN MORALES
Applicant returned to address corrections 4/7/2022 KEVIN MORALES
Plan Check Approved 4/20/2022 KEVIN MORALES
Issued 7/18/2022 APPLICANT
CofO in Progress 6/7/2023 SABAS ALONSO
Permit Finaled 6/16/2023 DEROLD HAUFF
CofO Issued 6/16/2023 DEROLD HAUFF
Permit Finaled 6/16/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/29/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 12/29/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/4/2022 WALLIE JONG
Sewer availability Cleared 4/4/2022 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/31/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 9/13/2022 Approved SABAS ALONSO
Sewer 9/27/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/12/2022 Corrections Issued STUART CHAPMAN
Green Building Rough 10/12/2022 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 10/12/2022 Approved STUART CHAPMAN
Wood Frame 10/12/2022 Partial Approval STUART CHAPMAN
PLUMBING-Rough 10/18/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/22/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 11/22/2022 Approved SABAS ALONSO
Green Building Rough 11/22/2022 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 11/22/2022 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 11/22/2022 Partial Approval SABAS ALONSO
HVAC-Rough 11/30/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 12/6/2022 Approved SABAS ALONSO
Green Building Rough 12/6/2022 Approved SABAS ALONSO
HVAC-Rough 12/6/2022 Approved SABAS ALONSO
Insulation 12/9/2022 Approved LILIANA PORTILLO
Drywall Nailing 12/19/2022 Approved BRENDAN MORELLI
Final 1/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 1/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 1/20/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/28/2023 Not Ready for Inspection SABAS ALONSO
Final 2/28/2023 Corrections Issued SABAS ALONSO
Green Building Final 2/28/2023 Approved SABAS ALONSO
HVAC-Final 2/28/2023 Approved SABAS ALONSO
PLUMBING-Final 2/28/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Approved SABAS ALONSO
Smoke Detectors 2/28/2023 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 3/8/2023 Approved SABAS ALONSO
Final 3/8/2023 Corrections Issued SABAS ALONSO
Service/Power Release 3/8/2023 Corrections Issued SABAS ALONSO
Smoke Detectors 3/8/2023 Approved SABAS ALONSO
Final 4/25/2023 Corrections Issued SABAS ALONSO
Service/Power Release 4/25/2023 Approved SABAS ALONSO
Final 6/6/2023 OK to Issue CofO SABAS ALONSO