723 1/2 E 93RD ST 90002

Certificate Information: 723 1/2 E 93RD ST 90002

Application / Permit
21010-20000-05629
Plan Check / Job No.
B21VN14798
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan (N) 20' X 27'2" ADU PER GCS 65852.2 & 65852.22
Permit Issued
Issued on 10/8/2022
Issuing Office
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2021 APPLICANT
Assigned to Plan Check Engineer 11/5/2021 HERNAN ARREOLA
Corrections Issued 11/5/2021 HERNAN ARREOLA
Applicant returned to address corrections 7/13/2022 SUNMIN LEE
Plan Check Approved 9/25/2022 HERNAN ARREOLA
Issued 10/8/2022 APPLICANT
CofO in Progress 5/26/2026 LUIS CASTRO
CofO Issued 5/28/2026 DEROLD HAUFF
Permit Finaled 5/28/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/2/2021 WALLIE JONG
Permit Cleared 12/2/2021 WALLIE JONG
Low Impact Development Cleared 6/29/2022 TA ANH
Eng Process Fee Ord 176,300 Cleared 6/30/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 7/5/2022 WALLIE JONG
Sewer availability Cleared 7/6/2022 WALLIE JONG
Construction near power lines Cleared 9/7/2022 RIDWAN HARDY

Contact Information

Contractor Benavides Builders Inc; Lic. No.: 1061451-B       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/30/2023 Conditional Approval LILIANA PORTILLO
Sewer 1/30/2023 Approved LILIANA PORTILLO
Underground Mechanical 1/30/2023 Partial Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 2/3/2023 Approved LILIANA PORTILLO
Footing/Foundation/Slab 2/3/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/15/2023 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 4/14/2023 Corrections Issued LILIANA PORTILLO
HVAC-Rough 4/14/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 4/14/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 5/5/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 5/5/2023 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 5/5/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 5/12/2023 Approved MICHAEL LEWIS
Insulation 5/22/2023 Conditional Approval MICHAEL LEWIS
Interior/Exterior Lathing 5/22/2023 Approved MICHAEL LEWIS
Drywall Nailing 6/5/2023 Approved RUBEN SALAS
Final 4/9/2026 Corrections Issued JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 4/9/2026 SGSOV Not Ready JOHN QUINTANILLA
Service/Power Release 4/9/2026 Not Ready for Inspection JOHN QUINTANILLA
Smoke Detectors 4/9/2026 Approved JOHN QUINTANILLA
Final 5/7/2026 Not Ready for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 5/7/2026 SGSOV Approved JOHN QUINTANILLA
Service/Power Release 5/7/2026 Not Ready for Inspection JOHN QUINTANILLA
Final 5/14/2026 Corrections Issued JOHN QUINTANILLA
Service/Power Release 5/14/2026 Approved JOHN QUINTANILLA
ELECTRICAL-Final 5/18/2026 Approved JOHN QUINTANILLA
Final 5/18/2026 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Final 5/22/2026 Approved LUIS CASTRO
Final 5/22/2026 OK to Issue CofO LUIS CASTRO