10505 W CANTARA ST 91352
Certificate Information: 10505 W CANTARA ST 91352
- Application / Permit
- 21010-20000-05628
- Plan Check / Job No.
- B21VN14797
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE WITH (E) ATTACHED CARPORT INTO A (N) DETACHED 35'-6" x 22'-0" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 6/16/2023
- Issuing Office
- Current Status
- CofO Issued on 1/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2023 | ALFRED RAMIREZ |
| Corrections Issued | 1/17/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 1/28/2023 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 5/25/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 5/26/2023 | PINANK PATEL |
| Plan Check Approved | 6/1/2023 | PINANK PATEL |
| Issued | 6/16/2023 | APPLICANT |
| CofO in Progress | 12/18/2025 | DAVID ANDERSON |
| Permit Finaled | 1/15/2026 | RUBEN SALAS |
| CofO Issued | 1/15/2026 | RUBEN SALAS |
| Permit Finaled | 1/15/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/30/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 4/22/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2023 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 5/8/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 5/8/2023 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 5/23/2023 | TORI CHEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/28/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 6/28/2023 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 8/16/2023 | Not Ready for Inspection | DAVID ANDERSON |
| MERV13>=Rough | 8/16/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2023 | Corrections Issued | WILLIAM WREN |
| MERV13>=Rough | 9/15/2023 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Partial Approval | DAVID ANDERSON |
| MERV13>=Rough | 9/21/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 11/9/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Partial Approval | DAVID ANDERSON |
| MERV13>=Rough | 11/9/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 12/4/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 12/28/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 12/28/2023 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 12/28/2023 | Approved | DAVID ANDERSON |
| Insulation | 1/11/2024 | Approved | DAVID ANDERSON |
| Drywall Nailing | 1/22/2024 | Approved | DAVID ANDERSON |
| Shower Pan | 2/9/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 2/28/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 12/5/2025 | Corrections Issued | MATTHEW NELSON |
| Final | 12/5/2025 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 12/5/2025 | Not Ready for Inspection | MATTHEW NELSON |
| MERV13>=Final | 12/5/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 12/5/2025 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/5/2025 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 12/5/2025 | Approved | MATTHEW NELSON |
| Final | 12/16/2025 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 12/16/2025 | Approved | DAVID ANDERSON |