10615 N ETIWANDA AVE 91326

Certificate Information: 10615 N ETIWANDA AVE 91326

Application / Permit
21010-20000-05627
Plan Check / Job No.
B21VN14795
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY DETACHED ADU. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 6/7/2022
Issuing Office
Current Status
CofO Issued on 4/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2021 APPLICANT
Assigned to Plan Check Engineer 11/12/2021 JOE VO
Corrections Issued 11/12/2021 JOE VO
Applicant returned to address corrections 12/7/2021 JOE VO
Applicant returned to address corrections 3/10/2022 JOE VO
Plan Check Approved 5/20/2022 JOE VO
Issued 6/7/2022 APPLICANT
CofO in Progress 6/21/2023 SEAN WIRCH
Permit Finaled 4/26/2024 DANIEL ORRANTE
CofO Issued 4/26/2024 DANIEL ORRANTE
Permit Finaled 4/26/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/9/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/11/2022 CARLOS AGUILERA
Sewer availability Cleared 1/11/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 2/17/2022 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 3/17/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 5/19/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: NA53080       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/24/2022 Approved SEAN WIRCH
PLUMBING-Rough 6/24/2022 Partial Approval SEAN WIRCH
Footing/Foundation/Slab 7/8/2022 Approved SEAN WIRCH
ELECTRICAL-Rough 8/26/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 Approved SEAN WIRCH
Green Building Rough 8/26/2022 Approved SEAN WIRCH
HVAC-Rough 8/26/2022 Approved SEAN WIRCH
PLUMBING-Rough 8/26/2022 Approved SEAN WIRCH
BUILDING-Rough-Frame 9/19/2022 Approved SEAN WIRCH
Interior/Exterior Lathing 9/19/2022 Approved SEAN WIRCH
Shower Pan 9/19/2022 Approved SEAN WIRCH
Verify Sprinkler Sign Off 9/19/2022 Approved SEAN WIRCH
Drywall Nailing 12/2/2022 Approved SEAN WIRCH
Insulation 12/2/2022 Approved SEAN WIRCH
Interior/Exterior Lathing 12/2/2022 Approved SEAN WIRCH
ELECTRICAL-Final 6/16/2023 Approved SEAN WIRCH
Final 6/16/2023 Corrections Issued SEAN WIRCH
HVAC-Final 6/16/2023 Approved SEAN WIRCH
PLUMBING-Final 6/16/2023 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 6/16/2023 SGSOV Not Ready SEAN WIRCH
Service/Power Release 6/16/2023 Approved SEAN WIRCH
Smoke Detectors 6/16/2023 Approved SEAN WIRCH
Final 6/21/2023 OK to Issue CofO SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 6/21/2023 SGSOV Approved SEAN WIRCH
Service/Power Release 7/26/2023 Approved SEAN WIRCH