17624 W WEDDINGTON ST 91316

Certificate Information: 17624 W WEDDINGTON ST 91316

Application / Permit
21010-20000-05620
Plan Check / Job No.
B21VN14777
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 22'-6" x 34' DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g)
Permit Issued
Issued on 7/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2021 APPLICANT
Assigned to Plan Check Engineer 11/11/2021 SELLA BENYAMIN
Corrections Issued 11/16/2021 SELLA BENYAMIN
Quality Review Completed 11/18/2021 STEVEN KIM
Building Plans Picked Up 11/22/2021 APPLICANT
Plan Check Approved 7/7/2022 SELLA BENYAMIN
Issued 7/29/2022 APPLICANT
CofO in Progress 1/31/2024 SEAN HAUPT
Permit Finaled 3/4/2024 JOHN JANSON
CofO Issued 3/4/2024 JOHN JANSON
Permit Finaled 3/4/2024 JOHN JANSON

Permit Application Clearance Information

Low Impact Development Cleared 4/20/2022 CHRIS VONG
Address approval Cleared 5/19/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/19/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/19/2022 CARLOS AGUILERA
Sewer availability Cleared 6/14/2022 CARLOS AGUILERA
Construction near power lines Cleared 7/7/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/14/2022 Not Ready for Inspection SEAN HAUPT
Underground Mechanical 9/14/2022 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 9/23/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 9/23/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Approved SEAN HAUPT
Rough-Elec/Plmb/HVAC 11/18/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 12/2/2022 Approved PETER FOLLING
Green Building Rough 12/2/2022 Approved PETER FOLLING
Interior/Exterior Lathing 12/2/2022 Partial Approval PETER FOLLING
Verify Sprinkler Sign Off 12/2/2022 Approved PETER FOLLING
Drywall Nailing 12/19/2022 Approved SEAN HAUPT
ELECTRICAL-Final 6/27/2023 Approved SEAN HAUPT
ELECTRICAL-Rough 6/27/2023 Approved SEAN HAUPT
PLUMBING-Final 6/27/2023 Approved SEAN HAUPT
PLUMBING-Rough 6/27/2023 Approved SEAN HAUPT
Final 6/28/2023 Corrections Issued SEAN HAUPT
Green Building Final 6/28/2023 Approved SEAN HAUPT
HVAC-Final 6/28/2023 Approved SEAN HAUPT
Final 1/30/2024 OK to Issue CofO SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 1/30/2024 SGSOV Approved SEAN HAUPT
Smoke Detectors 1/30/2024 Approved SEAN HAUPT