17109 W MANDARIN CT 91344

Certificate Information: 17109 W MANDARIN CT 91344

Application / Permit
21010-20000-05599
Plan Check / Job No.
B21VN14710
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY 1200 SQ. FT. ADU WITH NEW ATTACHED GARAGE
Permit Issued
Issued on 4/8/2022
Issuing Office
Current Status
CofO Issued on 7/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2021 APPLICANT
Assigned to Plan Check Engineer 11/2/2021 JOE VO
Corrections Issued 11/2/2021 JOE VO
Plan Check Approved 4/6/2022 JOE VO
Issued 4/8/2022 APPLICANT
CofO in Progress 6/23/2025 STEVEN BACK
Permit Finaled 7/18/2025 DANIEL ORRANTE
CofO Issued 7/18/2025 DANIEL ORRANTE
Permit Finaled 7/18/2025 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/13/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 11/15/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 11/16/2021 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 11/23/2021 VASIL MIHALEV
Hydrant and Access approval Cleared 2/14/2022 JOHN CONNEALLY
Construction near power lines Cleared 3/9/2022 RIDWAN HARDY
Low Impact Development Cleared 4/1/2022 TA ANH
Roof/Waste drainage to street Cleared 4/5/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/15/2022 Approved DAVID SCANTLIN
Underground Mechanical 5/18/2022 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 6/1/2022 Approved DAVID SCANTLIN
Footing/Foundation/Slab 6/1/2022 Approved DAVID SCANTLIN
Pre-Inspection 1/23/2024 Approved SEAN HAUPT
Sewer 5/7/2024 Approved JEFFREY PARD
Underground Mechanical 5/7/2024 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 5/30/2024 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/6/2024 Approved STEVEN BACK
HVAC-Rough 6/18/2024 Approved STEVEN BACK
PLUMBING-Rough 6/18/2024 Approved STEVEN BACK
BUILDING-Rough-Frame 8/9/2024 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 8/9/2024 Approved STEVEN BACK
Green Building Rough 8/9/2024 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 8/21/2024 Approved DAVID SCANTLIN
Green Building Rough 8/21/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 8/21/2024 Partial Approval DAVID SCANTLIN
Verify Sprinkler Sign Off 8/21/2024 Approved DAVID SCANTLIN
Insulation 9/19/2024 Approved STEVEN BACK
Drywall Nailing 10/2/2024 Approved JEFFREY PARD
Interior/Exterior Lathing 3/17/2025 Approved CHRIS CHRISTENSEN
Shower Pan 3/17/2025 Approved CHRIS CHRISTENSEN
Final 3/21/2025 Not Ready for Inspection STEVEN BACK
Green Building Final 3/21/2025 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Not Ready STEVEN BACK
Service/Power Release 3/21/2025 Not Ready for Inspection STEVEN BACK
Smoke Detectors 3/21/2025 Not Ready for Inspection STEVEN BACK
Final 6/16/2025 Corrections Issued STEVEN BACK
Green Building Final 6/16/2025 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Not Ready STEVEN BACK
Service/Power Release 6/16/2025 Not Ready for Inspection STEVEN BACK
Smoke Detectors 6/16/2025 Approved STEVEN BACK
Final 6/23/2025 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/23/2025 SGSOV Approved STEVEN BACK
Service/Power Release 6/23/2025 Approved STEVEN BACK