6264 N LUBAO AVE 91367

Certificate Information: 6264 N LUBAO AVE 91367

Application / Permit
21010-20000-05593
Plan Check / Job No.
B21VN14676
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1-STORY IRREGULAR SHAPED 96'-0" X 50'-0", 3,500 SQ. FT. SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/28/2022
Issuing Office
Current Status
CofO Issued on 11/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 COLIN LOREDO
Corrections Issued 11/8/2021 COLIN LOREDO
Quality Review Completed 11/8/2021 OMID HEDAYAT
Building Plans Picked Up 11/12/2021 APPLICANT
Plan Check Approved 2/28/2022 COLIN LOREDO
Issued 2/28/2022 APPLICANT
CofO in Progress 11/28/2022 SEAN WIRCH
Permit Finaled 11/28/2022 JOHN JANSON
CofO Issued 11/28/2022 JOHN JANSON
Permit Finaled 11/28/2022 JOHN JANSON

Permit Application Clearance Information

Permit Cleared 11/19/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 11/22/2021 CARLOS AGUILERA
Sewer availability Cleared 11/22/2021 CARLOS AGUILERA
Low Impact Development Cleared 1/26/2022 TA ANH
Disturb/Remove Protected Trees Cleared 1/28/2022 ADALBERTO VERA
Trees in Parkway Cleared 1/28/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 2/14/2022 DWAYNE LAURENT
Roof/Waste drainage to street Cleared 2/16/2022 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/18/2022 Approved SEAN HAUPT
Deputy Reinf. Concrete 4/6/2022 Conditional Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 4/6/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 4/6/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 4/15/2022 Approved SEAN HAUPT
Wood Frame 4/15/2022 Partial Approval SEAN HAUPT
PLUMBING-Rough 4/27/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 4/29/2022 Approved SEAN WIRCH
HVAC-Rough 4/29/2022 Not Ready for Inspection SEAN WIRCH
HVAC-Rough 5/3/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 5/5/2022 Approved SEAN HAUPT
Green Building Rough 5/5/2022 Approved SEAN HAUPT
Shower Pan 5/5/2022 Approved SEAN HAUPT
Verify Sprinkler Sign Off 5/5/2022 Approved SEAN HAUPT
Insulation 5/10/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 5/10/2022 Approved SEAN HAUPT
Insulation 5/11/2022 Not Ready for Inspection SEAN HAUPT
Interior/Exterior Lathing 5/11/2022 Not Ready for Inspection SEAN HAUPT
Drywall Nailing 5/18/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 5/18/2022 Not Ready for Inspection SEAN HAUPT
Gas Test 6/29/2022 Approved SEAN HAUPT
HVAC-Rough 9/23/2022 Approved SEAN HAUPT
PLUMBING-Final 9/23/2022 Approved SEAN HAUPT
ELECTRICAL-Final 10/6/2022 Approved SEAN HAUPT
Final 10/6/2022 Corrections Issued SEAN HAUPT
Green Building Final 10/6/2022 Approved SEAN HAUPT
HVAC-Final 10/6/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Approved SEAN HAUPT
Service/Power Release 10/6/2022 Not Ready for Inspection SEAN HAUPT
Smoke Detectors 10/6/2022 Approved SEAN HAUPT
Final 11/23/2022 OK to Issue CofO SEAN WIRCH
Service/Power Release 11/23/2022 Approved SEAN WIRCH