14056 W CHAMBERLAIN ST 91340
Certificate Information: 14056 W CHAMBERLAIN ST 91340
- Application / Permit
- 21010-20000-05555
- Plan Check / Job No.
- B21VN14569
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* (N) 1-STORY (30' X 40') DETACHED (ZC: 1200 SF) ADU PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 4/20/2022
- Issuing Office
- Current Status
- CofO Issued on 10/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | VIVIAN LAO |
| Corrections Issued | 11/30/2021 | VIVIAN LAO |
| Quality Review Completed | 12/5/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 4/7/2022 | VIVIAN LAO |
| Plan Check Approved | 4/19/2022 | VIVIAN LAO |
| Issued | 4/20/2022 | APPLICANT |
| CofO in Progress | 12/1/2023 | JENNIFER RABUCHIN |
| No Progress | 3/21/2024 | ROBERT GOLD |
| CofO in Progress | 3/21/2024 | ROBERT GOLD |
| CofO in Progress | 3/21/2024 | ROBERT GOLD |
| CofO in Progress | 10/18/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 10/23/2024 | DANIEL ORRANTE |
| CofO Issued | 10/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2021 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 2/10/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 2/11/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/1/2022 | ROSE MARIE SMITH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/16/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 6/28/2022 | Approved | MATT KELLERMAN |
| METHANE-Barrier | 6/28/2022 | Approved | MATT KELLERMAN |
| METHANE-Subgrade | 6/28/2022 | Approved | MATT KELLERMAN |
| PLUMBING-Rough | 6/28/2022 | Not Ready for Inspection | MATT KELLERMAN |
| BUILDING-Rough-Frame | 7/11/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 7/11/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Rough | 7/11/2022 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 7/11/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 7/14/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/14/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/3/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 8/3/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/15/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 8/15/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/13/2022 | Corrections Issued | DEANDRE HOFFMAN |
| HVAC-Rough | 9/13/2022 | Approved | DEANDRE HOFFMAN |
| PLUMBING-Rough | 9/13/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 9/16/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 9/16/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 11/9/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/5/2022 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 12/5/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/2/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/9/2023 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 6/27/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/16/2023 | Corrections Issued | JUAN VALENZUELA |
| Final | 9/14/2023 | Corrections Issued | ROBERT GOLD |
| HVAC-Final | 9/14/2023 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 11/21/2023 | Approved | JENNIFER RABUCHIN |
| Final | 11/21/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 11/21/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 11/21/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 11/21/2023 | Approved | JENNIFER RABUCHIN |
| Final | 12/1/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 12/1/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/1/2023 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 12/1/2023 | Not Required | JENNIFER RABUCHIN |