18314 W JOVAN ST 91335

Certificate Information: 18314 W JOVAN ST 91335

Application / Permit
21010-20000-05526
Plan Check / Job No.
B21VN14503
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1 STORY ADU (52'-0"x13'-8"), 635.4 SQFT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
Permit Issued
Issued on 6/28/2022
Issuing Office
Current Status
CofO Issued on 3/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 PETER MOSESIAN
Corrections Issued 11/10/2021 PETER MOSESIAN
Quality Review Completed 11/12/2021 OMID HEDAYAT
Building Plans Picked Up 11/16/2021 APPLICANT
Plan Check Approved 6/10/2022 PETER MOSESIAN
Issued 6/28/2022 APPLICANT
CofO in Progress 2/25/2026 JON MCHUGH
Permit Finaled 3/4/2026 JOHN JANSON
CofO Issued 3/4/2026 JOHN JANSON
Permit Finaled 3/4/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/20/2021 DAGOVERTO GUERRERO
ZI Cleared 11/22/2021 LAUREN PADICK
Eng Process Fee Ord 176,300 Cleared 11/23/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 11/23/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 2/3/2022 JOHN CONNEALLY
Low Impact Development Cleared 2/9/2022 TA ANH
Roof/Waste drainage to street Cleared 2/11/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 5/23/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/1/2024 Not Ready for Inspection JON MCHUGH
Underground Mechanical 10/1/2024 Partial Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 10/11/2024 Approved JON MCHUGH
BUILDING-Rough-Frame 11/5/2024 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Corrections Issued JON MCHUGH
Green Building Rough 11/5/2024 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 11/5/2024 Not Ready for Inspection JON MCHUGH
Rough-Elec/Plmb/HVAC 11/5/2024 Not Ready for Inspection JON MCHUGH
Verify Sprinkler Sign Off 11/5/2024 Not Ready for Inspection JON MCHUGH
HVAC-Rough 12/2/2024 Corrections Issued JON MCHUGH
PLUMBING-Rough 12/2/2024 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 12/9/2024 Not Ready for Inspection JON MCHUGH
HVAC-Rough 12/9/2024 Not Ready for Inspection JON MCHUGH
PLUMBING-Rough 12/9/2024 Approved JON MCHUGH
BUILDING-Rough-Frame 12/18/2024 Corrections Issued MORRIS JACKSON
HVAC-Rough 12/18/2024 Corrections Issued MORRIS JACKSON
Interior/Exterior Lathing 12/18/2024 Partial Approval MORRIS JACKSON
BUILDING-Rough-Frame 1/8/2025 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Rough 1/8/2025 Not Ready for Inspection JON MCHUGH
Green Building Rough 1/8/2025 Approved JON MCHUGH
HVAC-Rough 1/8/2025 Not Ready for Inspection JON MCHUGH
Verify Sprinkler Sign Off 1/8/2025 Approved JON MCHUGH
BUILDING-Rough-Frame 1/10/2025 Approved JON MCHUGH
ELECTRICAL-Rough 1/10/2025 Approved JON MCHUGH
HVAC-Rough 1/10/2025 Approved JON MCHUGH
Interior/Exterior Lathing 1/10/2025 Approved JON MCHUGH
Insulation 1/16/2025 Approved MORRIS JACKSON
Drywall Nailing 1/22/2025 Approved JON MCHUGH
ELECTRICAL-Final 3/11/2025 Not Ready for Inspection JON MCHUGH
Service/Power Release 3/11/2025 Not Ready for Inspection JON MCHUGH
Sewer 3/11/2025 Approved JON MCHUGH
Smoke Detectors 3/11/2025 Not Ready for Inspection JON MCHUGH
Underground Mechanical 3/11/2025 Not Ready for Inspection JON MCHUGH
Underground Mechanical 3/20/2025 Corrections Issued JON MCHUGH
ELECTRICAL-Final 5/7/2025 Approved MORRIS JACKSON
Final 5/7/2025 Corrections Issued MORRIS JACKSON
Green Building Final 5/7/2025 Approved MORRIS JACKSON
HVAC-Final 5/7/2025 Approved MORRIS JACKSON
PLUMBING-Final 5/7/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 5/7/2025 SGSOV Not Ready MORRIS JACKSON
Service/Power Release 5/7/2025 Corrections Issued MORRIS JACKSON
Smoke Detectors 5/7/2025 Approved MORRIS JACKSON
Final 8/21/2025 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 8/21/2025 SGSOV Not Ready JON MCHUGH
Service/Power Release 8/21/2025 Not Ready for Inspection JON MCHUGH
Final 8/27/2025 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV Not Ready MORRIS JACKSON
Final 9/12/2025 Not Ready for Inspection MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Not Ready MORRIS JACKSON
Service/Power Release 9/12/2025 Not Ready for Inspection MORRIS JACKSON
Final 9/18/2025 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Not Ready JON MCHUGH
Service/Power Release 9/18/2025 Not Ready for Inspection JON MCHUGH
Final 1/29/2026 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 1/29/2026 SGSOV Not Ready JON MCHUGH
Service/Power Release 1/29/2026 Approved JON MCHUGH
Final 2/11/2026 Not Ready for Inspection JON MCHUGH
SGSOV-Seismic Gas S/O Valve 2/11/2026 SGSOV Approved JON MCHUGH
Final 2/25/2026 OK to Issue CofO JON MCHUGH