5416 N GENESTA AVE 91316
Certificate Information: 5416 N GENESTA AVE 91316
- Application / Permit
- 21010-20000-05525
- Plan Check / Job No.
- B21VN14493
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 34' X 22'-6" ONE STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
- Permit Issued
- Issued on 6/23/2022
- Issuing Office
- Current Status
- CofO Issued on 11/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | SELLA BENYAMIN |
| Corrections Issued | 11/9/2021 | SELLA BENYAMIN |
| Building Plans Picked Up | 11/10/2021 | APPLICANT |
| Quality Review Completed | 6/14/2022 | OMID HEDAYAT |
| Plan Check Approved | 6/23/2022 | SELLA BENYAMIN |
| Issued | 6/23/2022 | APPLICANT |
| CofO in Progress | 11/16/2023 | VINCENT HANLEY |
| Permit Finaled | 11/21/2023 | JOHN JANSON |
| CofO Issued | 11/21/2023 | JOHN JANSON |
| Permit Finaled | 11/21/2023 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/11/2022 | LONDY ALVARADO |
| Address approval | Cleared | 2/17/2022 | AMIR KASHFI |
| Miscellaneous | Cleared | 2/17/2022 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 2/17/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 2/18/2022 | AMIR KASHFI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/29/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 6/29/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 6/29/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 7/6/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 7/6/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2022 | Not Ready for Inspection | SEAN HAUPT |
| Drywall Nailing | 10/5/2022 | Not Ready for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 12/5/2022 | Not Ready for Inspection | JON MCHUGH |
| Interior/Exterior Lathing | 12/14/2022 | Not Ready for Inspection | JON MCHUGH |
| Pre-Inspection | 12/14/2022 | Approved | JON MCHUGH |
| Shower Pan | 12/14/2022 | Not Ready for Inspection | JON MCHUGH |
| Interior/Exterior Lathing | 12/19/2022 | Approved | JON MCHUGH |
| Shower Pan | 12/19/2022 | Not Ready for Inspection | JON MCHUGH |
| Shower Pan | 12/21/2022 | Not Ready for Inspection | JON MCHUGH |
| Shower Pan | 12/27/2022 | Approved | JON MCHUGH |
| Insulation | 1/13/2023 | Conditional Approval | JON MCHUGH |
| Drywall Nailing | 1/23/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 7/21/2023 | Approved | VINCENT HANLEY |
| Green Building Final | 7/21/2023 | Approved | VINCENT HANLEY |
| HVAC-Final | 7/21/2023 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 7/21/2023 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/24/2023 | Approved | JON MCHUGH |
| Final | 8/24/2023 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 8/24/2023 | Approved | JON MCHUGH |
| MERV13>=Final | 8/24/2023 | Approved | JON MCHUGH |
| MERV13>=Rough | 8/24/2023 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 8/24/2023 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 8/24/2023 | Not Required | JON MCHUGH |
| Smoke Detectors | 8/24/2023 | Partial Approval | JON MCHUGH |
| Verify Sprinkler Sign Off | 8/24/2023 | Approved | JON MCHUGH |
| Smoke Detectors | 8/30/2023 | Approved | JON MCHUGH |
| Final | 10/17/2023 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 10/17/2023 | SGSOV Approved | VINCENT HANLEY |
| Final | 11/16/2023 | OK to Issue CofO | VINCENT HANLEY |