5414 N GENESTA AVE 91316

Certificate Information: 5414 N GENESTA AVE 91316

Application / Permit
21010-20000-05524
Plan Check / Job No.
B21VN14493
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 11' X 21' DETACHED REC ROOM
Permit Issued
Issued on 6/23/2022
Issuing Office
Current Status
CofO Issued on 11/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 SELLA BENYAMIN
Corrections Issued 11/9/2021 SELLA BENYAMIN
Building Plans Picked Up 11/10/2021 APPLICANT
Plan Check Approved 6/14/2022 SELLA BENYAMIN
Issued 6/23/2022 APPLICANT
CofO in Progress 10/18/2023 VINCENT HANLEY
Permit Finaled 11/21/2023 JOHN JANSON
CofO Issued 11/21/2023 JOHN JANSON
Permit Finaled 11/21/2023 JOHN JANSON

Permit Application Clearance Information

Low Impact Development Cleared 2/11/2022 LONDY ALVARADO
Miscellaneous Cleared 2/17/2022 AMIR KASHFI
Roof/Waste drainage to street Cleared 2/17/2022 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 2/18/2022 AMIR KASHFI

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/29/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 6/29/2022 Approved SEAN HAUPT
Underground Mechanical 6/29/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 7/6/2022 Approved SEAN HAUPT
Underground Mechanical 7/6/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 7/28/2022 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 9/30/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 12/2/2022 Not Ready for Inspection JON MCHUGH
Interior/Exterior Lathing 12/14/2022 Not Ready for Inspection JON MCHUGH
Pre-Inspection 12/14/2022 Approved JON MCHUGH
Shower Pan 12/14/2022 Not Ready for Inspection JON MCHUGH
Interior/Exterior Lathing 12/19/2022 Approved JON MCHUGH
Drywall Nailing 1/23/2023 Not Ready for Inspection JON MCHUGH
Drywall Nailing 1/25/2023 Approved JON MCHUGH
ELECTRICAL-Final 7/21/2023 Approved VINCENT HANLEY
Green Building Final 7/21/2023 Approved VINCENT HANLEY
HVAC-Final 7/21/2023 Corrections Issued VINCENT HANLEY
PLUMBING-Final 7/21/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 8/24/2023 Approved JON MCHUGH
Final 8/24/2023 Corrections Issued JON MCHUGH
Green Building Rough 8/24/2023 Approved JON MCHUGH
MERV13>=Final 8/24/2023 Approved JON MCHUGH
MERV13>=Rough 8/24/2023 Approved JON MCHUGH
SGSOV-Seismic Gas S/O Valve 8/24/2023 SGSOV Not Ready JON MCHUGH
Service/Power Release 8/24/2023 Not Required JON MCHUGH
Smoke Detectors 8/24/2023 Approved JON MCHUGH
Verify Sprinkler Sign Off 8/24/2023 Approved JON MCHUGH
Final 10/17/2023 OK to Issue CofO VINCENT HANLEY
HVAC-Final 10/17/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/17/2023 SGSOV Approved VINCENT HANLEY